ERM Sprint 123

Sprint Goal / Focus

  • Stripes 7 Upgrade
  • Bug fixes
  • RTL migration

Sprint Schedule

  • Sprint: 123
    • Start Monday 13 Sep
    • Finish Fri 24 Sep
    • Sprint Board
    • Jira Sprint: 1003
  • Release: 2021.3 Kiwi  
    • Sprint 123 (Mon Sep 13): Stripes v7 Upgrade Deadline
    • Sprint 124: Module Release Deadline
    • Sprint 127: Bugfix Deadline

Sprint Capacity

Team AvailabilitySchedule | Calendar

Notes / Exceptions:

  • 20-24 Sep: Peter on Leave

Lead Roles:

QA Environment: folio-snapshot

Navigation

 Sprint Planning Agenda
  1. Sprint Goal / Focus
  2. Sprint Capacity
  3. Review sprint candidates 
  4. Agree technical approach / define key implementation tasks
  5. Finalise estimates / costings
  6. Confirm sprint scope
  7. Confirm first actions






Sprint Planning  

(error) - not in sprint  (tick) or @ - in sprint   

Sprint Focus

Feature ID

Issue ID

Sprint Backlog?

Notes / Estimates / Actions

UXPROD-3264 - Getting issue details... STATUS

ERM-1821 - Getting issue details... STATUS

Aditya matukumalli

All branches pushed except ui-stripes-registry and dashboard which are pending platform-complete.

There is an issue with having ui AND stripes in name that is causing conflict, though this was previously advised by John M. 

Adi to discuss on #devops options to either change repository name or amend code that does name checking. 

Dashboard is unreleased, but dependent on the decision for ui-stripes-registry. 

Proceed with merge depending on whether deprecation happens before Stripes merge

UXPROD-2948 - Getting issue details... STATUS

ERM-1798 - Getting issue details... STATUS



ERM-1861 - Getting issue details... STATUS

Estimate 1d

May need update to filter.js 

UXPROD-3061 - Getting issue details... STATUS

ERM-1857 - Getting issue details... STATUS

When an agreement references more than 10 PO lines, we construct a query that caps results to 10. We should now show all requested lines. 

Add new CONST to manifest similar to RecordsPerRequest for orderlines from 100 to 1000. 

Starting points are AgreementLineRoute and AgreementLineViewRoute, and make changes to ask for higher maximum return limit parameter. 

Apply to view and edit. 

FAT-81 - Getting issue details... STATUS

ERM-1260 - Getting issue details... STATUS


FAT-81 - Getting issue details... STATUS

ERM-1278 - Getting issue details... STATUS


FAT-81 - Getting issue details... STATUS

ERM-1279 - Getting issue details... STATUS


FAT-81 - Getting issue details... STATUS

ERM-1280 - Getting issue details... STATUS



ERM-1770 - Getting issue details... STATUS

ERM-1771 - Getting issue details... STATUS
(error)

May need changes to toolkit also, so best done by a K-Int resident.

Could have conflicts with core vagrant update. 

UXPROD-2948 - Getting issue details... STATUS

ERM-1799 - Getting issue details... STATUS

(error)

ERM-1848 - Getting issue details... STATUS

Will require stable vagrant - latest version should be sufficient to develop with.

Frontend can be done in anticipation. 

Presentation should be similar to existing pattern, so no new wireframes needed. 

TODO: 

  • Add new example to custom properties (0.5h backend)
  • Changes to ui-agreements and erm-components (1h + overnight build on snapshot/testing)


ERM-1845 - Getting issue details... STATUS






Aditya matukumalli

TODO: raise draft PR for implementation review

Related (still blocked):

ERM-1757 - Getting issue details... STATUS

ERM-1758 - Getting issue details... STATUS

ERM-1759 - Getting issue details... STATUS

ERM-1760 - Getting issue details... STATUS

ERM-1761 - Getting issue details... STATUS


ERM-1816 - Getting issue details... STATUS





Brought Forward

Feature IDIssue IDSprint Backlog?

Notes / Estimates / Actions


ERM-1754 - Getting issue details... STATUS

TODO:

  • Modify to remove duplicate entries
  • Enhance integration test to match issue 

ERM-1845 - Getting issue details... STATUS

Branch for stripes-components reviewed by John C.

Edge cases to be handled STCOM-865.


ERM-1860 - Getting issue details... STATUS Review on Wednesday

ERM-1258 - Getting issue details... STATUS

Minor changes needed to 1345-1349


ERM-1259 - Getting issue details... STATUS

To pick up Tuesday

For QA / Release

Feature IDIssue IDSprint Backlog?

Notes / Estimates / Actions


ERM-1849 - Getting issue details... STATUS



ERM-1801 - Getting issue details... STATUS



ERM-1786 - Getting issue details... STATUS



ERM-1787 - Getting issue details... STATUS



ERM-1697 - Getting issue details... STATUS



ERM-506 - Getting issue details... STATUS

Including ERM-1859 - Getting issue details... STATUS


ERM-1648 - Getting issue details... STATUS

Testrails updates needed.

Brought In

Feature IDIssue IDSprint Backlog?

Notes / Estimates / Actions


ERM-1862 - Getting issue details... STATUS




ERM-1863 - Getting issue details... STATUS



Removed

Feature IDIssue IDSprint Backlog?

Notes / Estimates / Actions


ERM-1825 - Getting issue details... STATUS

New tests prepared and submitted for Boulder user testing.  

UXPROD-2948 - Getting issue details... STATUS

ERM-1799 - Getting issue details... STATUS


Bug fixes ahead of Kiwi release to take priority



Sprint Summary


ERM


key summary type assignee status components
Loading...
Refresh


Dashboard

key summary type assignee status components
Loading...
Refresh

Other

key summary type assignee status components
Loading...
Refresh