ERM Sprint 101
Sprint Goal / Focus
Sprint Schedule
Sprint: 101
Release: Honeysuckle / Iris
Quarter: 2021 Q1
Start Monday 2 Nov
Finish Friday 13 Nov
Navigation
Sprint Planning
- not in sprint
or @ - in sprint
Sprint Focus
Honeysuckle BugFest issues for ERM
Aim is to do fewer patch releases.
Review schedule for patch release on Wed 4 Nov.
https://issues.folio.org/browse/ERM-1203?src=confmacro
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
|---|---|---|---|
| @Aditya matukumalli | Unknown: only tenant (server) timezone has been adjusted, not device/browser (client) settings. UI (date widget fields) sends and saves a date to something different to what is entered. Appears to be at any time. Can be replicated on honeysuckle and snapshot environments.
TODO:
| |
| @Ethan Freestone | Not UI related: related Slack conversation. Grails 4 introduces a change to how flush works. This issue is more about multiple / forced flushes. Error: EntityExistsException when editing an amendment after the first edit. All toolkit libraries are same as mod-agreements/mod-licenses. TODO:
| |
| @Owen Stephens | Happening on Honeysuckle but not snapshot. Multiple agreement lines appear if there are multiple packages to which the title belongs. @ostephens to TODO
| |
| @Claudia Malzer | See discussion in 2020-10-28 ERM Weekly Delivery Update Quickfix is to bump the max pick list length to 100, which should be more than sufficient for normal use case.
| |
|
| @Aditya matukumalli | Already fixed. Just awaiting patch release.
|
| @Owen Stephens | To be resolved as documentation. | |
| @Owen Stephens | Fixed as part of stripes-connect 6.0.1. In sprint for QA. | |
| @Claudia Malzer | ui.license.picklist.manage is needed to both view and manage pickLists licenses.refdata.collection.view needs to be added to the licenses.terms.manage overarching permission set. needs to in the backend also. For testing, would need to be manually added to okapi to avoid waiting for environment to be built. | |
| @Owen Stephens | Needs re-checking. Also to verify with supplementary documents in agreements. | |
|
|
| |
|
|
|
|
Brought Forward
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
|---|---|---|---|
| Pending wireframes for ERM-1036. Also need a UI for URL sampling. Also dependent on https://folio-org.atlassian.net/browse/ERM-1048 | ||
@Ethan Freestone | Lower priority than Honeysuckle bugfixes during this sprint. Options include:
| ||
@Owen Stephens | In QA. | ||
| https://folio-org.atlassian.net/browse/ERM-1151 / https://folio-org.atlassian.net/browse/ERM-1186 | @Gill Osguthorpe |
|
| @Owen Stephens | Previously waiting on wireframes - now pending wireframe review with PO. | |
| @Peter Böhm | Integration tests are failing. |
Brought In
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
|---|---|---|---|
| @Peter Böhm |
| |
| @Ethan Freestone |
|
Removed
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
|---|---|---|---|
|
|
| . |