Sprint Goal / Focus
- UX Improvements
License Search (for Dashboard)
Sprint Schedule
- Sprint: 103
- Release: Iris
- Quarter: 2021 Q1
- Start Monday 30 Nov
- Finish Friday 11 Dec
Sprint Capacity
Team Availability: Schedule | Calendar
Notes / Exceptions:
- Last full sprint before holiday season
Lead Roles:
- Front End Code Review: Aditya matukumalli
- Back End Code Review: Ethan Freestone
- QA: Owen Stephens
QA Environment: folio-snapshot
Navigation
Sprint Planning
- not in sprint
or @ - in sprint
Sprint Focus
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
Owen and Gill to review ui options for expressing search / filter conditions. | |||
Ian, Steve and Ethan have had a conversation about this. Tracks back to how list is bound in web-toolkit Switch to Grails 4 with significant updates seems to have fixed it. Fixed in Honeysuckle. Would take weeks to patch in earlier versions because of the framework upgrades. Could potentially spend a couple of days to dig into, refine estimate and explore possible options. Ian to spend a day to examine options and impact. | |||
Aditya matukumalli | Estimate: 1d Permissions have been moved inside a Display Action Button function, but no permission wrapped around that. Potentially render only if Action has children, rather than checking individual and variable permissions?
TODO:
| ||
Needs more elaboration |
Brought Forward
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
In QA | |||
In Code Review. Steve to progress as priority to unblock ERM-1229 | |||
In Development | |||
In Development. Needs ERM-1243. | |||
Effort: straightforward Four column layout is already being used in other apps. We're starting to introduce to ERM. Issue includes removing duplicate status display. | |||
Effort: Change would intentionally remove the direct link to the TI. MCL data link is tightly coupled (within the existing eresource-link component) to the TI, so uncoupling from PCI is less straightforward. Would need to navigate from TI to PCI. Could be done from links in 'covered eresources' - so should also have Impact: the component is used extensively in other places. No additional info or component should be needed, as the existing component has all the info necessary - the link just needs to be changed. Applies only to internal/local KB resources. | |||
Peter Böhm | |||
Peter Böhm | Needs to be tested in pre-UTC timezone (such as New York) |
Brought In
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
Peter Böhm | Added 9 Dec | ||
Added 9 Dec |