ERM Sprint 81
ERM Sprint 81
Sprint Goal / Focus
- Support for non-serial resources
Sprint Schedule
- Sprint: 81
- Release: Fameflower
- Quarter: 2020 Q1
- Start Monday 13 Jan, 2pm UK
- Finish Friday 24 Jan, 12pm UK
Sprint Capacity
Team Availability: Schedule | Calendar
Notes / Exceptions:
- WolfCon w/c 20 Jan. Owen Stephens NA.
Lead Roles:
- Front End Code Review: md331 (Deactivated)
- Back End Code Review: steve.osguthorpe
- QA: Owen Stephens / Gill Osguthorpe
QA Environment: folio-testing
Navigation
Sprint Planning
- not in sprint
or @ - in sprint
Brought Forward
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
Almost code complete. Query about updating the database to reflect code changes. Potentially look at examples in migrations folder in mod-agreements. | |||
Functionality complete - cannot be tested yet, as there is an issue with tests suite. | |||
STCON-92 is now resolved, so this is unblocked. |
Sprint Focus
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
Add to e-resource preview panel in the first instance.
| |||
steve.osguthorpe | . | ||
Q: how to identify a record? See notes on ERM Sprint 79-80. Owen to followup with Steve. | |||
Needs further definition. May be dependent on ERM-485. | |||
Jag Goraya to followup with steve.osguthorpe re streaming dependency. | |||
Novelty:
Needs wireframe, and may be dependent on ERM-591. Investigation goals for Sprint 81:
| |||
No longer effectively blocked by STCON-57 |
, multiple selections available,
Related content
ERM Sprint 187
ERM Sprint 187
More like this
ERM Sprint 188
ERM Sprint 188
More like this
Sprint 209
Sprint 209
More like this
Sprint 210
Sprint 210
More like this
Sprint 205
Sprint 205
More like this
Sprint 206
Sprint 206
More like this