Sprint: 186
Start Mon 4 Feb 2024
Finish Fri 15 Mar
Jira Sprint: 110
Release: 2024.1 Quesnalia
Sprint 11 of 11 since Release Development Cycle Starts (Sprint 176) to Feature Freeze (Sprint 186: 15 Mar 2024)
Sprint 187: Module Release Deadline (22 Mar 2024) [FOLREL-565]
Sprint 189: Bugfix Release Deadline (19 Apr 2024) [FOLREL-581]
Development Meetings
Wed 6 Mar - dev update
Mon 11 Mar - backlog review
Wed 13 Mar - dev update
Planning Questions
Does the issue meet the criteria for Definition of Ready?
What front and back end components are affected?
What changes need to be made? (additions, removals or modifications)
What development tests need to be written?
What data does the developer need to verify their work?
What are the known unknowns?
What is needed to QA? (environment, data, scripts)
Navigation
- 1 Sprint Goal / Focus
- 2 Sprint Schedule
- 3 Sprint Capacity
- 3.1 Sprint Focus
- 3.1.1 Tests
- 3.1.2 Release Tasks (Non-Flower Release)
- 3.1.3 Release Tasks (Orchid CSP)
- 3.1.4 Release Tasks (Poppy Bug Fix)
- 3.1.5 Maintenance
- 3.2 Changes
- 3.1 Sprint Focus
- 4 Sprint Summary
Sprint Planning
- not in sprint
or @ - in sprint
- not ready
- pending triage / planning
Sprint Focus
Planning Notes Template
Triage
Approach
Components and Changes
Frontend
Backend
Tests / Data / Dependencies
Known Unknowns
QA: snapshot | local | testing | other
Release Target:
Development Estimate
Issue ID | Sprint Backlog? | Notes / Estimates / Actions | Carried Over |
|---|---|---|---|
|
| ||
|
| ||
@Claudia Malzer |
|
| |
|
|
| |
| TBC
|
| |
|
|
| |
|
|
| |
| Testrails | Sprint 180 | |
| Testrails | Sprint 182 | |
@Monireh Rasouli | Mar 4, 2024
Mar 6, 2024
| Sprint 182 | |
@Jack Golding | Environment set up Ready to progress To follow ERM-3131 Mar 6, 2024
Mar 11, 2024
|
| |
@Jack Golding | Mar 6, 2024
|
| |
@Ethan Freestone | Next up ...
|
| |
@Claudia Malzer @Ethan Freestone | Progress:
Mar 4, 2024 TODO:
Mar 6, 2024
Mar 13, 2024
|
| |
Mar 6, 2024
|
| ||
@Ethan Freestone | Mar 6, 2024 TODO: Needs code review Mar 11, 2024
|
| |
Grails Track Mar 4, 2024
Mar 6, 2024
Mar 11, 2024
Mar 13, 2024
| |||
|
|
|
|
|
|
|
|
| QA | Sprint 176 | |
@Ethan Freestone | Code Review | Sprint 178 | |
@Ethan Freestone
| Code Review | Sprint 178 | |
Steve Osguthorpe | Code Review | Sprint 180 | |
| Ready TO PROGESS
Feb 19, 2024
| Sprint 182 | |
| In Progress
| Sprint 178 | |