ERM Sprint 72
Sprint Goal / Focus
Sprint Schedule
- Sprint: 72
- Release: Elderflower
- Quarter: 2019 Q3
- Start Monday 9 Sep, 2pm UK
- Finish Friday 20 Sep, 12pm UK
Sprint Capacity
Team Availability: Schedule | Calendar
Notes / Exceptions:
- Module Release Prep / Deadline: 11 Sep
Lead Roles:
- Front End Code Review: md331 (Deactivated)
- Back End Code Review: steve.osguthorpe
- QA: Owen Stephens
QA Environment: folio-testing
Navigation
Sprint Planning
- not in sprint
or @ - in sprint
Sprint Focus
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
"Current" status is being used to test logic, which may cause internationalisation problems, if using label/value.
TODO:
| |||
md331 (Deactivated) | FE: 3d including integration tests
| ||
BE: 2d
| |||
BE: 0.5d FE: 0.25d TODO:
| |||
Existing pattern of counts logging - number of upserts Non-trivial maybe is handling single title services | |||
Owen Stephens to revisit with Gill Osguthorpe | |||
|
Brought Forward
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
Estimate: 2d Aim to prioritise to meet module release deadline to include in Daisy release. | |||