2020-11-25 ERM Weekly Delivery Update

Meeting Details

Date

    

Time

10:30am ET, 3:30pm UK, 4:30pm Germany

LocationVideo Call in FOLIO Slack: #erm-developers
Previously2020-11-18 ERM Weekly Delivery Update
ReferencesJIRA Issue Board

Goals

Participants

Apologies

Discussion items

Time

Item

Notes

Action Items

<5 minsIntroductions



WIP Update 

Release Candidates

Code Review: 

  • ERM-1243 - Getting issue details... STATUS
    • slight extension to code review
    • Steve O likely to look at it, but may not 

QA / UAT 

  • ERM-1048 - Getting issue details... STATUS
    • template URLs not being generated on snapshot
    • some minor UI tweaks returned to 
    • creation of url is not observable
    • this may be a permission issue (using permissionRequired rather than okapi module permissions)
    • as a testing workaround, the permission can be allocated to user
    • if still an issue, revert to Ethan to review modulePermission fix through 
  • ERM-1246 - Getting issue details... STATUS
    • no impediments expected
  • ERM-1223 - Getting issue details... STATUS
    • seems to work but difficult to test because of eholdings availability load throttling 
    • requires some work from EKB
    • may need to release as working if no further 

Items at Risk / Spillover

In Progress

  • ERM-1190 - Getting issue details... STATUS
    • form field is causing an integer validation error on Save
      • unless clicking out of field
      • this issue happens elsewhere
      • Behaviour accepted by PO
    • input is converted to integer using parseInt
    • Design accepted by UX lead
    • TODO:
      • use translation strings
      • using values in MCL
      • tests
    • A few days effort still expected because of configMgr complexity
  • ERM-1204 - Getting issue details... STATUS
    • backend part is now working
    • rebuilding vagrant fixed the environment issue
    • needed linkedAgreement and linkdLicensesGet
    • front end part demo'd
    • TODO
      • expected result 1 
      • integration tests
    • DECISION: split the work done so far out and follow up outstanding expectations after the permissions discussion in the ERM subgroup on Wed 2 Dec
    • Peter to complete integration tests today and submit for code review before COP. 
  • ERM-1229 - Getting issue details... STATUS
    • pretty much all of this is left to do
    • cannot be code reviewed until ERM-1243
    • expecting probably a couple of days 
    • will slip and rollover into Sprint 103

Sprint Backlog

  • ERM-1102 - Getting issue details... STATUS
    • Assigned to Adi for PR raising
    • ERM-1110 separated out
  • ERM-1137 - Getting issue details... STATUS - rollover
  • ERM-1148 - Getting issue details... STATUS - rollover
  • ERM-1176 - Getting issue details... STATUS - rollover
  • ERM-1227 - Getting issue details... STATUS - rollover
  • ERM-1228 - Getting issue details... STATUS - rollover
  • ERM-1143 - Getting issue details... STATUS - rollover
  • ERM-1237 - Getting issue details... STATUS - rollover

Needs Elaboration

  • ERM-1225 - Getting issue details... STATUS - expected by end of sprint
  • ERM-1233 - Getting issue details... STATUS - expected by end of sprint

Closed

  • ERM-1184 - Getting issue details... STATUS
  • ERM-1238 - Getting issue details... STATUS
    • Thunderjet have released their own fix, so this will not be hotfixed unless severe performance issues are reported under Honeysuckle
    • ERM fix will go out in next release, and should co-exist with the mod-orders fix
  • ERM-1224 - Getting issue details... STATUS


<10 minsAOB

New Issues

Added to sprint

Not added to sprint

  • ERM-1236 - Getting issue details... STATUS
    • reasdy for development
  • ERM-1242 - Getting issue details... STATUS


Suppress from discovery

  • Owen Stephens to add new story for suppress from discovery on edit screen
    • following from input for Felix
    • may entail changes to how originally implemented