2025-01-13 Release Management Stakeholder group
Release Management Stakeholder group
Attendees @Mark Veksler @Yogesh Kumar @Khalilah Gambrell @Oleksii Petrenko Stephen Pumpell
Meeting Time: 9:00 AM Eastern Time
Discussion items
Time reserved | Description | Presenter | Details/Comments |
15 min | Ramsons Bugfix Status and release timeline update | Oleksii | Manual test case execution at Ramsons Bugfest Environment is done Number of unresolved P1&P2 defects is around 60 - https://folio-org.atlassian.net/jira/dashboards/10465 Following teams have outstanding defects:
Based on fact that manual regression mostly was done at November-December, some test results could be outdated. To mitigate possible regressions and provide additional time for development teams, proposed following approach:
|
Notes: