2025-01-13 Release Management Stakeholder group

2025-01-13 Release Management Stakeholder group

Release Management Stakeholder group

Attendees Mark Veksler Yogesh Kumar Khalilah Gambrell Oleksii Petrenko Stephen Pumpell


https://openlibraryfoundation.zoom.us/j/88356244681?pwd=aFo1cEhVam1ENTN1ZHFOZWg0V1Jxdz09


Meeting Time: 9:00 AM Eastern Time

Discussion items

Time reservedDescriptionPresenterDetails/Comments
15 min

Ramsons Bugfix Status and release timeline update

Oleksii

Manual test case execution at Ramsons Bugfest Environment is done

Number of unresolved P1&P2 defects is around 60 - https://folio-org.atlassian.net/jira/dashboards/10465

Following teams have outstanding defects:

  • Eureka
  • Vega
  • Corsair
  • Folijet
  • Spitfire

Based on fact that manual regression mostly was done at November-December, some test results could be outdated.

To mitigate possible regressions and provide additional time for development teams, proposed following approach:

  1. Jan 13 - Jan 24 - Additional run of manual and automated regression testing
  2. Jan 24 - Ramsons bugfix deadline
  3. Jan 27 - Jan 31 - Final smoke testing week
  4. Feb 3 - Ramsons GA 

Notes: