2020-11-25 Retrospective Spitfire
Date | Nov 25, 2020 |
|---|---|
Participants | @Oleksii Petrenko @Khalilah Gambrell @Natalia Zaitseva @Denys Bohdan @Pavlo Smahin @Владислав Велицкий @Dima Tkachenko @Sobha Duvvuri @Dmitriy Litvinenko |
Retrospective
What did we do well?
Can work with scratch env with out problems +
Excellent team work on UC feature +
Dmitriy Litvinenko is added to team +
Stanislav Miroshnichenko is assisting with rancher issues
On-boarding went smooth and in constructive way
Identified bugfest issues were resolved quickly
Easy to work with scratch env
What should we have done better?
Caused additional challenges with rancher env setup
Not clear how to work with permissions (Workaround is used for now)
Actions
Caused additional challenges with rancher env setup → Reach out to @Stanislav Miroshnichenko
Not clear how to work with permissions (Workaround is used for now) → @Stanislav Miroshnichenko
October 2020
DT - In general module releases went well, but one issue (with logging) was not payed attention to immediately. This led to additional patch releases of several modules/libraries - Move to Release retrospective → @Oleksii Petrenko
Additional time is required for get practice with Rancher for successful roll out → Team
Rancher service should put some notifications regarding resources stopping and allocation. Reach out to @Sergiy Vysotskiy and @Stanislav Miroshnichenko → @Oleksii Petrenko
August 2020
50% Validate prepared stories quicker when it is deployed to Snapshort environment → @Khalilah Gambrell @patty.wanninger
Issue with MOD-USER-IMPORT: Expectation of user is contradict with team's one
Validate requirements by User Management SIG group or PO(Ian Walls) from MOD-USER-IMPORT before presenting them to the team → @Khalilah Gambrell
July 2020
Bugfix release cause misunderstanding when working with different jira projects and different git projects.
Post new process instruction to Spitfire channel
Need stabilize release process
June 2020
Prepare possible plan for extending current testing approach → @Denys Bohdan @maksym_dryha @Владислав Велицкий
Verify affected areas manually → Team
Report issues to stripes team while development → Team
Check all acceptance criteria while dev testing → Team, @Khalilah Gambrell
Sync with BE team and dependency detection → Team
Part of definition of done (Include accessibility testing to testing activities by FE team) → @Oleksii Petrenko
Run accessibility checker more frequently and include it to CI pipeline (Run once in the sprint by FE team) → FE team
Clarify more carefully hidden scenarios in acceptance criteria → Team, @Khalilah Gambrell
Create stories more carefully to avoid situation that we missed some at the end → Team, @Khalilah Gambrell
Include to release preparation plan interface update for 2 weeks before release deadline (Bump up latest version of interfaces were too later) → @Oleksii Petrenko