Discussion items
Item | Notes |
|---|---|
eUsage Use Case for using LDP | Status of eUsage App -cost per use is the most important report -in the eUsage app, usage data being collected about a resource from various providers or services -in agreements, the way the resource is being ordered, licensed, invoiced, etc. is set up -no link between eUsage resource and agreements yet
Questions -is the work better done in LDP or within a FOLIO app? -mod agreements could do a query against LDP and provide data back to the agreements UI, evaluates the permissions, and performs the query itself
Frequency -stats not needed in real time; most users gather data monthly
Is this a unique need from a FOLIO app? If so, might be strange to do anything special.
Nassib How to decide between doing it using LDP or doing it through the APIs for the modules?
-need to think about queries -might be easier if distribution of queries arranges over -if small number of attributes, might be more efficient to develop in FOLIO application
Is the "overnight data" problem relevant? If you need real-time data, is that a problem here?
-could push data into LDP as needed (faster than overnight) -FOLIO db needs to respond to request in real time; LDP is queried by analysts; use of LDP could create a latency in providing the data
Data Storage Concerns Is data size a problem?
Proof of Concept -outline representative query -set up amount of data needed for good test
Permissions for queries?
-no OKAPI interface to LDP; a permissions system would require developing this -queries could be direct ODBC queries, but we also need to add the LDP loader to load incremental data -eUsage can proxy to the LDP
Moving forward - prototype?
Timeline Constraints? -eUsage wants to finish application by December 2019 -ask Annika for specifics on timing
Next Steps -small workgroup discusses issues further and returns to Reporting SIG with recommendations -small workgroup is Richard, Nassib, Owen, Annika, Kevin, and Matt from this meeting -note that Richard and Annika have documented a good use case the small workgroup can start with
Preparation for next meeting -document what is needed in a schematic way (e.g., typical query, typical dataset with appropriate size) -describe data needed, query patterns
|
Action items