2022-10-26 ERM Weekly Delivery Update

Meeting Details

Date

 

Time

9:05am ET, 2:05pm UK, 3:05pm Germany

Location

Video Call in

Previously2022-10-19 ERM Weekly Delivery Update
ReferencesJIRA Issue Board

Goals

Apologies

  • Monireh

Discussion items

Time

Item

Notes

<5 minsIntroductions

Call Priorities


WIP 

 In Progress
  • ISSUE: 
    • Progress / Impediments: 
    • TODO: 
    • New unknowns: 
    • Help or input needed: 
    • ETA for review: 
  • What progress or impediment on previously stated actions?
  • What's left to do?
  • Any new unknowns?
  • What help or input is needed?
  • When expected to be ready for review?

In Progress

  • ERM-2258 - Getting issue details... STATUS
    • Moved to Code Review 
  • ERM-2261 - Getting issue details... STATUS
    • Progress / Impediments: 
      • Stripes issues, now resolved
    • ETA for review: Thursday

Pending

 Blocked
  • ISSUE
    • Blocking conditions
    • Action needed
  • Are the blocking conditions still relevant? 
  • What action is needed to unblock, and by whom?


 Needs Elaboration
  • ISSUE: 
    • Who / When: 
    • ETA Ready for Dev: 
  • Who needs to be involved in the elaboration process? 
  • What is the timeframe for getting input?
  • When is the issue expected to be ready for development?


 Sprint Backlog


  • Who is picking up what next?
  • When is next issue expected to start / complete?
  • Anything needed to start next issue (dependencies or clarifications)?

Blocked

  • NA

Needs Elaboration

  • NA

Sprint Backlog - Next Up

  • Nolana Release Tasks

Others

  • Claudia:
  • Ethan: Release Tasks
  • Monireh:  NA
  • Peter:

At Risk

  • What is now at risk of not being started this sprint?
  • Do any of these take priority over other sprint backlog items?

Sprint Backlog - to follow

  • NA

Sprint Backlog -  At Risk

  • NA

Removed


In Review

  • Any impediments to review or QA?
  • Any useful context, implementation choices or limitations for the reviewer/tester to know ?


Code Review:

QA / UAT 

Waiting for snapshot to rebuild

Bugfix Cycle 

  • NA



Release Candidates

  • What has passed QA since last dev call?
  • What has been closed since last dev call?

For Release / Pending Testrails

Previously

Closed: Nolana R2022.3

Stories / Bugs

RTL / Tasks

Release Tasks

Closed (No ERM Release)

  • <10 mins

AOB


New Issues

Added to sprint

Not added to sprint

Other

Component Updates

  • NA

Release Planning

  • Need to update release procedures to reflect use of GitHub Actions
  • SEC is getting a major version bump to v7
    • This may break snapshot
    • This may cascade a major version bump
  • The release tag for mod-service-interaction already exists in okapi
    • OS to look out for new dashboard  functionality not being present when bugfest environment is built

Testing