FOLIO Q4 2018 (Aster) Weekly Status Report

FOLIO Q4 2018 (Aster) Weekly Status Report

 

Suggest ideas for FOLIO reports and dashboards here

 

See the Q4 2018 Release Dashboard and the Chalmers Release Dashboard in JIRA for more charts and click-through to feature details.

See FOLIO Quality Dashboard for bi-weekly updates on software quality.

Q4 2018 Release Milestones

 

Weekly Updates

Report Date

Overall Status Update

Report Date

Overall Status Update

 

 

2019-01-14

@Cate Boerema (Deactivated)

Click to view status update history

Q4 2018 Release Features (Functional) by Status

https://folio-org.atlassian.net/issues/?jql=filter%3D10984+

Q4 2018 Release Features (NFR) by Status

https://folio-org.atlassian.net/issues/?jql=filter%3D10985+

Status

Definition

Status

Definition

Open 

Feature is waiting to be picked up by PO.  

Draft 

Feature is  being worked on by the PO.  Discussions are happening with the SIGs and sub-groups, mock-ups are being created.  Analysis is underway.

Analysis Complete

PO analysis is complete.  Stories are written and mockups have been created.

In Progress

Analysis is complete and development is underway.  While it is often the case that we begin development on some aspects of a feature before the PO’s analysis work has been completed, please do not move a feature into Development (In Progress) until after Analysis is Complete.  This is important so we can maintain visibility into what features that have remaining PO work.

In Review

Most or all stories in the feature are In Review (being tested).

Closed

All stories in the feature have passed test and are closed.  Feature is complete.

 

 

Product Owner Updates

 

Date

Product Owner

Notable Risks, Issues and/or Changes

Date

Product Owner

Notable Risks, Issues and/or Changes

2019-01-11

@Cate Boerema (Deactivated)

I split UXPROD-1238, formerly known as "Location and Service Point CRUD Enhancements Q4 2018":

  • The carry over work is now contained in UXPROD-1416 (Location and Service Point CRUD Enhancements Continued)

  • To better describe what was actually completed in Q4, I renamed UXPROD-1238 "Enable Filtering of Location Records by Institution, Campus and Library"

  • While only one of the 4 stories was completed, it was bonus work - this feature was not planned for Q4 (we were able to make some progress on while UI developers were waiting for backend dependencies to complete)

I split UXPROD-1138 (Requests Pick List: CSV Export) because the csv export is missing a single column (inventory dependencies were not in place). Carry over work is not contained in Add Copy Number to Requests CSV (UXPROD-1417)

2019-01-14

Darcy Branchini

I split UXPROD-675 (CRUD patron notice templates). The carry over work is now contained in UXPROD-1421 (Pre-defined patron notices). There are also a few bugs that reported from the original CRUD patron notice templates. Those are captured as UICIRC-160, UICIRC-159, UICIRC-143, and UICIRC-161.

2019-01-17

@sthomas (Deactivated)

I split UXPROD-744 (Loan Policy: Impact on loans part 2 - Q4-2018 Release). The carry over work is now contained in UXPROD-1440 (Loan Policy: Impact on loans part 3 - post-Q4-2018).

2019-01-18

@Dennis Bridges

UXPROD-678 was split for the Q4 release. Some of the field mapping work needs to be updated as updates have been made to the orders schema. The work that has carried over is now covered by UXPROD-1444.

Click to view product owner update history

 

Chalmers 

The focus of Q3 and Q4 2018 is delivering the features required by Chalmers to go live.  For this reason, we will take a closer look at those features in this portion of the report.  See the Chalmers Release Dashboard in JIRA for these and more click-through reports.

 

NOTE: There are also https://folio-org.atlassian.net/issues/?jql=project+%3D+uxprod+AND+type+%3D+%22new+feature%22+AND+%28resolution+not+in+%28duplicate%2C+%22Won%27t+Do%22%29+OR+resolution+is+EMPTY%29+AND+status+%21%3D+closed+AND+%22Rank%3A+Chalmers%22+is+EMPTY+AND+%28labels+not+in+%28NFR%2C+mandatory%2C+technical%29+OR+labels+is+EMPTY%29+ORDER+BY+cf%5B10002%5D+ASC%2C+assignee+ASC%2C+summary+ASC+ (UXPROD features) that have not yet been ranked by Chalmers.  As these features are ranked, we should expect the features needed below to increase.


Remaining Features Needed by Chalmers to Go-Live 

Chalmers Go-Live Features at Risk in Q4 

These may be carried over into Q1 2019 (either entirely or in part)

Chalmers for Go-Live Feature With No PO

Features Needed by Chalmers for Go-Live

Q4 2018 Release History

 

Metric

Description

 

Metric

Description

 

Closed release features

Features released on January 14, 2018

https://folio-org.atlassian.net/issues/?jql=project+%3D+uxprod+AND+type+%3D+%22new+feature%22+AND+Status+%3D+Closed+AND+%28resolution+not+in+%28duplicate%2C+%22Won%27t+Do%22%29+OR+resolution+is+EMPTY%29+AND+status+%3D+closed+and+fixVersion+%3D+%22Q4+2018%22+ORDER+BY+cf%5B10002%5D+ASC%2C+assignee+ASC%2C+summary+ASC+++++ Total

Targeted release features

Features targeted for Q4 release on October 9, 2018. Notes:

  • The baseline features were not finalized until about a week after the start of the development period, as the Acquisitions issues needed to be distributed across development teams

  • Included features will need to be further adjusted due to resourcing changes, but this can be considered the baseline

https://folio-org.atlassian.net/issues/?jql=project+%3D+uxprod+AND+type+%3D+%22new+feature%22+AND+%28resolution+not+in+%28duplicate%2C+%22Won%27t+Do%22%29+OR+resolution+is+EMPTY%29+AND+fixVersion+was+%22Q4+2018%22+ON+%282018-10-09%29+ORDER+BY+cf%5B10002%5D+ASC%2C+assignee+ASC%2C+summary+ASC++++++++ Total

Split release features

Number of Q4 features that were not fully completed and needed to be "split" (carry-over features were created for unfinished work)

https://folio-org.atlassian.net/issues/?jql=project+%3D+uxprod+AND+type+%3D+%22new+feature%22+AND+Status+%3D+Closed+AND+fixVersion+%3D+%22Q4+2018%22+and+labels+%3D+split++

Percent Closed

Closed features/Target features

70%

(up from 30% last quarter)