Welcome to Sprint 138!
Review remaining tickets with Release=Lotus R1 2022 <== all work done
Review tickets with Release=Lotus R1 2022 Bug Fix <== all work done
Plans for the current sprint
- Fix P1/P2 bugs
- Work on Morning Glory release tasks.
- Finish JIRA tickets carried over from Sprint 137.
- Work on critical "tech debt" issues (such as testing).
Overall plan for Morning Glory (R2 2022) release
- Fix critical bugs.
- Address "Tech debt" issues (such as testing).
- Work on Inventory features listed below.
Features planned for Morning Glory (R2 2022) release
Functional
- UXPROD-1892 (BE: Instance: Add related instances data element) <== first priority! 2 OPEN; 2 Closed tickets
- UXPROD-3080 (Edit. Analytical records; bound with - part 2: link multiple bibs to the same item) <== 2nd priority! 5 OPEN tickets *) Critical work for many libraries.
- UXPROD-3513 (Inventory Elastic Search (Morning Glory): Timebox for Priority Inventory Search and Filter Enhancements) <== 3rd priority. 6 OPEN (+1 MSEARCH ticket); 3 BLOCKED tickets. We will do as much of this work as we are able to
*) Joint work with Sif development team who will do UXPROD-3640.
Tech Debt
- UXPROD-3524 (Tech Debt: Create UI-USERS tests with RTL/Jest - R2 2022) <== In progress: 7 In Code Review, 0 In progress, 75 OPEN tickets, 25 Closed
Features TBD:
Morning Glory - Moved to other dev teams (TBD on 4/19)
- UXPROD-3328 (Tech Debt: Create ElasticSearch tests with RTL/Jest for ui-plugin-find-instance - R2 2022) <==Analysis Complete – move to Firebird (Nolana ?) - 36 OPEN UIPFI tickets
- UXPROD-3322 (Tech Debt: Create UI-INVENTORY tests with RTL/Jest - R2 2022) <==Analysis Complete – move to Foljiet (Nolana ?) - 140 OPEN UIIN tickets
- UXPROD-3302 (Tech Debt: Create ElasticSearch tests with RTL/Jest - R2 2022) <==Analysis Complete – move to Firebird (Nolana ?) - 41 OPEN UIIN tickets
Nolana?
- UXPROD-3601 (Prokopovych: USERS e-2-e tests (NFR) - Not scheduled) <==Analysis Complete – 8 FAT tickets
- UXPROD-3605 (Prokopovych: INVENTORY e-2-e tests (NFR) - Not scheduled) <==Analysis Complete – 15 FAT tickets
------------
General information on Morning Glory
Key timeline reminders
- April 29: Deadline for requests to add new modules to the reference environments
- June 3: Platform-core new development freeze
- June 10: Platform complete new development freeze
- July 4 - July 15: Bugfest period
- August 8: Morning Glory released to the public