Nolana (R3 2022)
Roadmap
EPICS
Release preparation
Modules release
Timeline
Sprint | Dates | Dates | Name | Description |
---|---|---|---|---|
Sprint 146 |
| Notify community regarding sharing information of new modules | Include module to FOLIO Module/JIRA project-Team-PO-Dev Lead responsibility matrix | |
Sprint 147 |
| Deadline for requests to add new modules to the reference environments | ||
Sprint 148 |
| Orchid R1 2023 release scope composition deadline | Lead PO prepared list of features for Orchid R1 2023 release and get approval from PC | |
Sprint 149 |
| API freeze for platform (Okapi/Stripes/RMB/Spring) readiness review | RC review released platform components and facilitate meeting with unreleased components owners to discuss available impediments/issues/problems to understand when component could be released | |
| API freeze for platform (Okapi/Stripes/RMB/Spring) | Okapi/Stripes/RMB/SpringWay freeze and deadline for initial releases of platform components. No breaking changes to the platform after this date. Feature development freeze for R3 2022 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R3 2022 period. Separate release branch has to be created after feature freeze date. All R3 2022 bug fixed have to be applied to both release and Master branches. Next R1 2023 release period feature development is expected on Master branch. | ||
Features test cases preparation deadline | To start test case automation for Nolana features test cases need to be prepared. | |||
Deadline for acceptance of new modules by Technical Council | New Module Technical Evaluations - Technical Council - FOLIO Wiki | |||
Sprint 150 | - | Teams upgrade to the platform components | Teams upgrade to the platform components versions that were released. | |
Bugfest environment preparation kick-off | Conduct meeting for review Bugfest preparation plan Create appropriate jira tickets in Kitfox backlog Review list of new modules Review data cleanup Review new data | |||
Prepare vagrant box with Morning Glory codebase | ||||
| Major interface version provided to be updated | |||
Modules feature development freeze R3 2022 - Platform core modules | Feature development freeze for R3 2022 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R3 2022 period. Separate release branch has to be created after feature freeze date. All R3 2022 bug fixed have to be applied to both release and Master branches. Next R1 2023 release period feature development is expected on Master branch. | |||
- | Orchid release scope decomposition and estimation | |||
- | Schema upgrade testing week (BE core modules) | |||
| Orchid R1 2023 release scope refinement deadline | POs prepare list of UXPROD features aligned with Orchid R1 2023 team capacity. PO present prepared scope at next PO Weekly meeting at <TBD> | ||
Review upgrade to platform components status. | RC review upgraded components and facilitate meeting with non-upgraded components owners to discuss available impediments/issues/problems to understand when component could be upgraded | |||
Modules feature development freeze R3 2022 - Platform complete modules | Feature development freeze for R3 2022 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R3 2022 period. Separate release branch has to be created after feature freeze date. All R3 2022 bug fixed have to be applied to both release and Master branches. Next R1 2023 release period feature development is expected on Master branch. | |||
Nolana R3 2022 features acceptance deadline | ||||
Sprint 151 | - | Schema upgrade testing week | Major modules versions should be released. Schema upgrade have to be released and tested locally by each team. | |
- | Teams modules releases | |||
- | Platform Core Back End (Storage) modules releases | |||
- | Platform Core Back End (Business logic) modules releases | |||
- | Platform Core Front End modules releases | |||
Platform Complete Back End (Storage) modules releases | ||||
- | Platform complete BE (Business logic) modules releases | |||
- | Platform complete Front End modules releases | |||
(Monday) | Modules release readiness review | RC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released). Major interface version provided to be updated | ||
| New blank Morning Glory bugfest environment is prepared | |||
| Scripts are ready for new modules deployment | |||
| Schema upgrade testing review | RC review upgraded modules and facilitate meeting with non-upgraded modules owners to discuss available impediments/issues/problems to understand when schema could be upgraded. | ||
| Final Review modules release readiness | RC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released | ||
Module release deadline | All modules must see R3 2022-compatible releases by this date | |||
Sprint 152 |
| Contact with Kitfox devops | Review release information. Up to date versions should be set | |
- | Release integration week | Bugfest environment preparation, testing of schema and data migration by Kitfox team | ||
| Deployment to Nolana bugfest env is completed. Data set is ready | |||
- | Sanity testing at Nolana bugfest env | |||
Sprint 152 - Sprint 154 | - | R3 2022 Release testing and hardening period | ||
- | Functional testing (Bug Fest) | Execute all TestRail test cases | ||
- | Performance testing | |||
- | Ongoing triage and bug fixing of bugs begins immediately | |||
| Bugfix releases readiness | RC review bugfix dashboard and facilitate meeting with unresolved modules owners to discuss available impediments/issues/problems to understand when module could be released | ||
Create R3-2022 platform complete release branch | TBD | |||
| Bugfix releases deadline | |||
- | Smoke testing | |||
Sprint 155 |
| Release is public |
Interface dependency matrixes
2022_R3_InterfacesDependencyMatrix-MastervsMaster
2022_R3_InterfacesDependencyMatrix-2022R2vsMaster
Modules planned for release
Main release 28 October 2022
Hot Fix #1
Modules release deadline -
GA Date -
Release notes
Nolana (R3 2022) Release Notes
Release digest
FOLIO - Nolana R3 2022 Release digest
Video recording
FOLIO - Nolana R3 2022 Release digest - Video recording