Nolana (R3 2022)

Roadmap

EPICS

Release preparation

key summary type due status
Loading...
Refresh

Modules release

key summary type due status
Loading...
Refresh

Timeline

SprintDatesDatesNameDescription
Sprint 146

 

Notify community regarding sharing information of new modulesInclude module to FOLIO Module/JIRA project-Team-PO-Dev Lead responsibility matrix
Sprint 147

 

Deadline for requests to add new modules to the reference environments

Create Jira ticket at FOLIO Jira project ex.  FOLIO-3255 - Getting issue details... STATUS

Sprint 148

 

Orchid R1 2023 release scope composition deadlineLead PO prepared list of features for Orchid R1 2023 release and get approval from PC
Sprint 149

 

API freeze for platform (Okapi/Stripes/RMB/Spring) readiness reviewRC review released platform components and facilitate meeting with unreleased components owners to discuss available impediments/issues/problems to understand when component could be released

 

API freeze for platform (Okapi/Stripes/RMB/Spring)

Okapi/Stripes/RMB/SpringWay freeze and deadline for initial releases of platform components. 

No breaking changes to the platform after this date.

Feature development freeze for R3 2022 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R3 2022 period. Separate release branch has to be created after feature freeze date. All R3 2022 bug fixed have to be applied to both release and Master branches. Next R1 2023 release period feature development is expected on Master branch.

Features test cases preparation deadlineTo start test case automation for Nolana features test cases need to be prepared.
Deadline for acceptance of new modules by Technical CouncilNew Module Technical Evaluations - Technical Council - FOLIO Wiki
Sprint 150

 

Teams upgrade to the platform componentsTeams upgrade to the platform components versions that were released.

Bugfest environment preparation kick-off

Conduct meeting for review Bugfest preparation plan

Create appropriate jira tickets in Kitfox backlog

Review list of new modules

Review data cleanup

Review new data

Prepare vagrant box with Morning Glory codebase

 

Major interface version provided to be updated
Modules feature development  freeze R3 2022 - Platform core modulesFeature development freeze for R3 2022 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R3 2022 period. Separate release branch has to be created after feature freeze date. All R3 2022 bug fixed have to be applied to both release and Master branches. Next R1 2023 release period feature development is expected on Master branch.

- 

Orchid release scope decomposition and estimation

- 

Schema upgrade testing week (BE core modules)

 

Orchid R1 2023 release scope refinement deadline

POs prepare list of UXPROD features aligned with Orchid R1 2023 team capacity. PO present prepared scope at next PO Weekly meeting at <TBD>

Review upgrade to platform components status.RC review upgraded components and facilitate meeting with non-upgraded components owners to discuss available impediments/issues/problems to understand when component could be upgraded
Modules feature development freeze R3 2022 - Platform complete modulesFeature development freeze for R3 2022 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R3 2022 period. Separate release branch has to be created after feature freeze date. All R3 2022 bug fixed have to be applied to both release and Master branches. Next R1 2023 release period feature development is expected on Master branch.
Nolana R3 2022 features acceptance deadline

Sprint 151

 

Schema upgrade testing weekMajor modules versions should be released. Schema upgrade have to be released and tested locally by each team.

 

Teams modules releases

 

Platform Core Back End (Storage) modules releases

 

Platform Core Back End (Business logic) modules releases

 

Platform Core Front End modules releases

Platform Complete Back End (Storage) modules releases

 

Platform complete BE (Business logic) modules releases

 

Platform complete Front End modules releases

  (Monday)

Modules release readiness reviewRC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released). Major interface version provided to be updated

 

New blank Morning Glory bugfest environment is prepared 

 

Scripts are ready for new modules deployment

 

Schema upgrade testing reviewRC review upgraded modules and facilitate meeting with non-upgraded  modules owners to discuss available impediments/issues/problems to understand when schema could be upgraded.

 


Final Review modules release readiness

RC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released
Module release deadlineAll modules must see R3 2022-compatible releases by this date

Sprint 152


 

Contact with Kitfox devopsReview release information. Up to date versions should be set

 

Release integration weekBugfest environment preparation, testing of schema and data migration by Kitfox team

 

Deployment to Nolana bugfest env is completed.

Data set is ready


 

Sanity testing at Nolana bugfest env

Sprint 152 - Sprint 154




 

R3 2022 Release testing and hardening period

 

Functional testing (Bug Fest)Execute all TestRail test cases

 

Performance testing

 

Ongoing triage and bug fixing of bugs begins immediately

 


Bugfix releases readinessRC review bugfix dashboard and facilitate meeting with unresolved modules owners to discuss available impediments/issues/problems to understand when module could be released
Create R3-2022 platform complete release branch

TBD

 

Bugfix releases deadline

Smoke testing
Sprint 155

 

Release is public

Interface dependency matrixes 

2022_R3_InterfacesDependencyMatrix-MastervsMaster

2022_R3_InterfacesDependencyMatrix-2022R2vsMaster

Modules planned for release

Main release 28 October 2022

key summary assignee status fixVersions
Loading...
Refresh

Hot Fix #1

Modules release deadline -  

GA Date -  

key summary assignee status fixVersions
Loading...
Refresh

Release notes


Nolana (R3 2022) Release Notes

Release digest

PDF

FOLIO - Nolana R3 2022 Release digest

Video recording

FOLIO - Nolana R3 2022 Release digest - Video recording