Morning Glory (R2 2022)

Morning Glory (R2 2022)

Roadmap

EPICS

Release preparation

key summary type due status
Loading...
Refresh

Modules release

key summary type due status
Loading...
Refresh

Timeline

Sprint

Dates

Dates

Name

Description

Sprint

Dates

Dates

Name

Description

Sprint 137

Apr 15, 2022 

Notify community regarding sharing information of new modules

Include module to FOLIO Module/JIRA project-Team-PO-Dev Lead responsibility matrix

Sprint 138

Apr 29, 2022 

Deadline for requests to add new modules to the reference environments

Create Jira ticket at FOLIO Jira project ex. FOLIO-3255: Add mod-inn-reach to testing/snapshot hosted environmentsClosed

Sprint 139

May 13, 2022 

Nolana R3 2022 release scope composition deadline

Lead PO prepared list of features for Nolana R2 2022 release and get approval from PC

Sprint 140



May 23, 2022 

API freeze for platform (Okapi/Stripes/RMB/Spring) readiness review

RC review released platform components and facilitate meeting with unreleased components owners to discuss available impediments/issues/problems to understand when component could be released

May 27, 2022 



API freeze for platform (Okapi/Stripes/RMB/Spring)

Okapi/Stripes/RMB/SpringWay freeze and deadline for initial releases of platform components. 

No breaking changes to the platform after this date.

Feature development freeze for R2 2022 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R2 2022 period. Separate release branch has to be created after feature freeze date. All R2 2022 bug fixed have to be applied to both release and Master branches. Next R3 2022 release period feature development is expected on Master branch.

Features test cases preparation deadline

To start test case automation for Morning Glory features test cases need to be prepared.

Deadline for acceptance of new modules by Technical Council

New Module Technical Evaluations - Technical Council - FOLIO Wiki

Sprint 141

May 30, 2022Jun 10, 2022 

Teams upgrade to the platform components

Teams upgrade to the platform components versions that were released.

May 30, 2022

Bugfest environment preparation kick-off

Conduct meeting for review Bugfest preparation plan

Create appropriate jira tickets in Kitfox backlog

Review list of new modules

Review data cleanup

Review new data

May 30, 2022

Prepare vagrant box with Lotus codebase



Jun 3, 2022 

Major interface version provided to be updated



Modules feature development  freeze R2 2022 - Platform core modules

Feature development freeze for R2 2022 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R2 2022 period. Separate release branch has to be created after feature freeze date. All R2 2022 bug fixed have to be applied to both release and Master branches. Next R3 2022 release period feature development is expected on Master branch.

Jun 2, 2022 -Jun 3, 2022 

Nolana release scope decomposition and estimation



Jun 6, 2022 -Jun 10, 2022 

Schema upgrade testing week (BE core modules)



Jun 6, 2022 

Nolana R3 2022 release scope refinement deadline

POs prepare list of UXPROD features aligned with Nolana R3 2022 team capacity. PO present prepared scope at next PO Weekly meeting at <TBD>

Jun 10, 2022



Review upgrade to platform components status.

RC review upgraded components and facilitate meeting with non-upgraded components owners to discuss available impediments/issues/problems to understand when component could be upgraded

Modules feature development freeze R2 2022 - Platform complete modules

Feature development freeze for R2 2022 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R2 2022 period. Separate release branch has to be created after feature freeze date. All R2 2022 bug fixed have to be applied to both release and Master branches. Next R3 2022 release period feature development is expected on Master branch.

Sprint 142

Jun 13, 2022Jun 24, 2022

Teams upgrade to the RMB v 34



Sprint 143

























Jun 27, 2022Jul 1, 2022 

Schema upgrade testing week

Major modules versions should be released. Schema upgrade have to be released and tested locally by each team.

Jun 27, 2022Jul 8, 2022 

Teams modules releases





Jun 27, 2022Jun 28, 2022 

Platform Core Back End (Storage) modules releases





Jun 29, 2022Jun 30, 2022 

Platform Core Back End (Business logic) modules releases





Jun 30, 2022Jul 1, 2022 

Platform Core Front End modules releases





Platform Complete Back End (Storage) modules releases





Jul 4, 2022Jul 6, 2022 

Platform complete BE (Business logic) modules releases





Jul 6, 2022Jul 8, 2022 

Platform complete Front End modules releases





Modules release readiness review

RC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released). Major interface version provided to be updated

Jul 5, 2022 

New blank Lotus bugfest environment is prepared 



Jul 7, 2022 

Scripts are ready for new modules deployment



Jul 8, 2022 

Schema upgrade testing review

RC review upgraded modules and facilitate meeting with non-upgraded  modules owners to discuss available impediments/issues/problems to understand when schema could be upgraded.

Jul 8, 2022 




Final Review modules release readiness

RC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released

Module release deadline

All modules must see R2 2022-compatible releases by this date

Sprint 144



Jul 11, 2022 

Contact with Kitfox devops

Review release information. Up to date versions should be set

Jul 11, 2022Jul 15, 2022 

Release integration week

Bugfest environment preparation, testing of schema and data migration by Kitfox team

Jul 13, 2022 

Deployment to Lotus bugfest env is completed.

Data set is ready



Jul 14, 2022Jul 15, 2022 

Sanity testing at Lotus bugfest env



Sprint 144 - Sprint 148









Jul 18, 2022Aug 12, 2022 

R2 2022 Release testing and hardening period





Jul 18, 2022Jul 29, 2022 

Functional testing (Bug Fest)

Execute all TestRail test cases



Jul 18, 2022Jul 29, 2022 

Performance testing





Aug 1, 2022Sep 9, 2022 

Ongoing triage and bug fixing of bugs begins immediately



Sep 7, 2022 



Bugfix releases readiness

RC review bugfix dashboard and facilitate meeting with unresolved modules owners to discuss available impediments/issues/problems to understand when module could be released

Create R2-2022 platform complete release branch

@John Malconian /Kitfox

Sep 9, 2022 

Bugfix releases deadline



Sprint 148 - Sprint 149

Sep 12, 2022Sep 23, 2022

Morning Glory Stabilization Testing & Smoke Testing



Sprint 149

Sep 26, 2022 

Release is public