Sprint Goal / Focus
- Stripes 7 Upgrade
- Bug fixes
- RTL migration
Sprint Schedule
- Sprint: 123
- Start Monday 13 Sep
- Finish Fri 24 Sep
- Sprint Board
- Jira Sprint: 1003
- Release: 2021.3 Kiwi
- Sprint 123 (Mon Sep 13): Stripes v7 Upgrade Deadline
- Sprint 124: Module Release Deadline
- Sprint 127: Bugfix Deadline
Sprint Capacity
Team Availability: Schedule | Calendar
Notes / Exceptions:
- Sprint is 8 not 10 days
- 1-10 Sep: Claudia on Leave
- 6 Sep: Adi on US public holiday
- 1-3 Sep: Monireh sick
- 1-2 Sep: Peter sick
Lead Roles:
- Front End Code Review: Aditya matukumalli
- Back End Code Review: Ethan Freestone
- QA: Owen Stephens
QA Environment: folio-snapshot
Navigation
Sprint Planning
- not in sprint or @ - in sprint
Sprint Focus
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
Aditya matukumalli | |||
- FAT-81Getting issue details... STATUS | |||
Aditya matukumalli | |||
Brought Forward
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
- ERM-1860Getting issue details... STATUS | |||
Some minor PR pushback. Many tests still to begin. Expected to complete 2021-09-06 | |||
For QA / Release
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
Testrails updates needed. |
Brought In
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
Removed
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
New tests prepared and submitted for Boulder user testing. | |||
Blocked awaiting eholdings credentials |