JIRA status

JIRA status

Overview 

POs have discussed an additional JIRA workflow status that indicates that a feature or story requires more discussion with development and has yet to be estimated. The feature/story is not ready for development to start. The new JIRA workflow status will be named In Refinement. Below tables outline proposed JIRA status workflows' changes. 

NOTE: Please review filters/dashboards/sprint boards once changes are made. 

JIRA status for UXPROD project

Feature JIRA status 

When do you set a feature to this status?

Feature JIRA status 

When do you set a feature to this status?

Draft 

Feature has not been defined. Still very vague. Very little analysis/research has been done. Not ready for development team to review. 

In Refinement

Feature is better defined and ready for the development team to review, to create user stories, and to estimate stories. Not ready for development to begin implementation. Feature may need to be further refined. The feature is currently being worked on by team (PO and/or dev). 

Open 

Feature is ready for development to begin implementation. 

Analysis complete 

We will no longer use this status. We will sunset with the conclusion of the Lotus release. 

In Progress

Feature is in development.

Blocked

Feature is blocked due to a dependency.

In Review

Development complete. PO/SME review implementation. 

Closed

PO/SME approves implementation. 

JIRA status for all projects except UXPROD

Story JIRA status 

When do you set a story to this status?

Story JIRA status 

When do you set a story to this status?

Draft

Issue has not been defined. Still very vague. Very little analysis/research has been done. Not ready for development team to review. 

In Refinement

Issue is better defined and ready for the development team to review and to estimate issue. Not ready for development to begin implementation. Issue may need to be further refined. The issue is currently being worked on by team (PO and/or dev). 

Open

Issue is ready for development to begin implementation.

In Progress

Issue is in development. Assume in current sprint. 

Blocked

Issue is blocked due to a dependency. 

In Code Review

 

Prep Deployment

 

In QA

Some teams use this when the code has been merged but not yet available on a hosted reference environment for a PO to review. 

Others may use it if a QA person is assigned to the team and that person is still reviewing implementation. 

In Review

Development complete. PO/SME review implementation. 

For Release

Can use if issue PO needs  to write documentation and/or test case (used by ERM only at this time) 

Awaiting release

Bugfest/Hotfix workflow step:  Issue requires a module release.

Awaiting deployment

Bugfest/Hotfix workflow step:  Issue requires deployment to release's bugfest environment. 

In Bugfix review

Bugfest/Hotfix workflow step:  Ready for PO/SME to verify issue has been resolved. PO/SME uses release's bugfest environment for verification.

Closed

PO/SME approves implementation.