Sprint Goal / Focus
- Tie up loose ends, and prepare ground for Q3.
Sprint Schedule
- Sprint: 66
- Quarter: 2019 Q2
- Start Thursday 13 June, 2pm UK
- Finish Friday 28 June, 2pm UK
- Retrospective: Wed 3 July, 2:30pm UK
Sprint Capacity
Team Availability: Schedule
Notes / Exceptions:
- 17-20 Jun FOLIO Washington + Travel (Ian, Owen, Jag)
- Claudia Malzer not available after 19 June
- md331 (Deactivated) not available 13-14 June
- Peter Böhm only available 13, 14, 19 June
Lead Roles:
- Front End Code Review: md331 (Deactivated)
- Back End Code Review: steve.osguthorpe
- QA: Owen Stephens
QA Environment: folio-testing
Navigation
Sprint Planning
- not in sprint
or @ - in sprint
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
BE 0h FE 8h TODO: differences in SASQ routing from Licenses to Agreements, so slightly different. Aditya matukumalli to support Claudia Malzer on accomodating the differences. Expected to be complete by end of week. | |||
BE 15h FE 0h Driven by https://folio-project.slack.com/archives/CAYCU07SN/p1557421022302700
Explainer documentation in Github. Dev questions raised as tasks/bugs in Jira. Peer review by dev team. | |||
Carried forward | |||
Carried forward | |||
Carried forward | |||
Carried forward. |
To Carry Forward
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
Requires - ERM-239Getting issue details... STATUS Clashes with - UINV-7Getting issue details... STATUS steve.osguthorpe Should the backend provide the data, or should the frontend fetch this (as done with organizations)? | |||