Meeting Details

Date

 

Time

9:15am ET, 2:15pm UK, 3:15pm Germany

Location

Video Call in

Previously2021-10-27 ERM Weekly Delivery Update
ReferencesJIRA Issue Board

Goals

Apologies

Discussion items

Time

Item

Notes

<5 minsIntroductions

Call Priorities
  • ERM-1899 - Getting issue details... STATUS
  • ERM-1687 - Getting issue details... STATUS
  • ERM-1915 - Getting issue details... STATUS
  • ERM-1850 - Getting issue details... STATUS
  • ERM-1902 - Getting issue details... STATUS
  • RTL / ERM-1661 - Getting issue details... STATUS
    • 1664 AgreementLine
    • 1681 URLCustomizer

WIP 

  • What progress or impediment on previously stated actions?
  • What's left to do?
  • Any new unknowns?
  • What help or input is needed?
  • When expected to be ready for review?

In Progress

  • ERM-1850 - Getting issue details... STATUS
    • TODO:
      • needs to be a criteria check
      • check hibernate docs for subquery or subcriteria implementation details
      • to test
        • manually test: find a title through clean ingest without options and search for that (before and after new code)
        • integration test: out of scope because of reliance on ingest 
      • expect for code review Thursday
  • ERM-1902 - Getting issue details... STATUS
    • Unknown: how to test in a multi-tenancy environment
    • Best approach will be monitor for breaks
    • Issue is basically done, including applying to 1883/1900
    • TODO:
      • review against current integration tests 
      • no event-related integration tests to be done (will take an additional day
  • ERM-1488 - Getting issue details... STATUS
  • ERM-1492 - Getting issue details... STATUS
    • PR depends on changes made yesterday to stripes-erm-components
    • will wait for those to avoid jenkins fail
  • ERM-1662 - Getting issue details... STATUS / ERM-1664 - Getting issue details... STATUS

Pending

Blocked

  • Are the blocking conditions still relevant? 
  • What action is needed to unblock, and by whom?

Needs Elaboration

  • Who needs to be involved in the elaboration process? 
  • What is the timeframe for getting input?
  • When is the issue expected to be ready for development?

Sprint Backlog

  • Who is picking up what next?
  • When is next issue expected to start / complete?
  • Anything needed to start next issue (dependencies or clarifications)?

Blocked

  • ERM-1687 - Getting issue details... STATUS
    • Updated following UX/Dev discussion
    • Current work done by Claudia is necessary but not sufficient
    • TODO: 
      • QA on ERM-1899 (PO)
      • Gill and Ethan to confer on which option to progress, as defined in comments (2021-10-25)

Needs Elaboration

  • NA

Sprint Backlog - Next Up

  • Claudia: 
    • RTL
  • Peter:  
  • Ethan:
  • Adi:
    • ERM-1915 - Getting issue details... STATUS
      • to prioritise ahead of current RTL issues
      • is this possible to do at the backend?
        • doesn't look like it should be handled in the front-end
        • polling between backend modules (with a single fetch via okapi) is slow and increases fetch times rather than multiple frontend fetches (which is current expectation)
        • switching between front and back end logic is not good for a hotfix
      • best way may be to make a copy, but we're not there yet with backend storage and sync
      • strategy:
        • fix in frontend for now (live sites affected)
        • address backend storage and sync
        • apply to this and contacts
      • Frontend unknowns
        • frontend character limit is 4096, but large number of POlines would be more than this character count: therefore need multiple requests chunked across order lines :: what is the chunk break? Break at 80
        • Sending requests in series would work, but a small number (eg, 5) in parallel could work.  
        • Sample set to add once 5.0.4 change
      • Components: 
        • multiple routes
      • Estimate: longer to verify ... 2d max
    • ERM-1913 - Getting issue details... STATUS
  • Monireh: 
    • RTL

At Risk

  • What is now at risk of not being started this sprint?
  • Do any of these take priority over other sprint backlog items?

Sprint Backlog - to follow

Sprint Backlog -  At Risk


In Review

  • Any impediments to review or QA?
  • Any useful context, implementation choices or limitations for the reviewer/tester to know ?


Code Review: 

QA / UAT 

  • ERM-1899 - Getting issue details... STATUS
    • Tested behaviour:
      • save should be stopped, but this doesn't seem to happen
      • validation error is shown, but save is not prevented
      • if name is empty, validation prevents save
    • Correct behaviour is working locally, but not on snapshot
      • validate should be on field not form
    • Returned to Adi to raise PR with correct changes
  • ERM-1882 - Getting issue details... STATUS
  • ERM-1884 - Getting issue details... STATUS

Bugfix Cycle 



Release Candidates

  • What has passed QA since last dev call?
  • What has been closed since last dev call?

Accepted

Need testrails cases

Closed: Lotus R1 2022

Features

  • NA

RTL / Other Tests

Closed: Kiwi R3 2021 Bug Fix

<10 mins

AOB


New Issues

Added to sprint

Not added to sprint