Sprint | Dates | Sprint Goals | Release related milestone(s) |
---|
151 | | - Stabiilize eholdings export
- authority control development
| Release Nolana modules |
152 | | - Complete SPIKE
ARCH-22
-
Getting issue details...
STATUS
- Stabilize eholdings export for Nolana release or make the decision to move it to Orchid
- authority control development
| Nolana bugfest |
153 | | - Nolana bugfest bugs
authority control development begin (reporting SPIKE) - Start
ARCH-36
-
Getting issue details...
STATUS
|
|
154 | |
- Complete
ARCH-36
-
Getting issue details...
STATUS
- 12/02/2022 - Nolana Bugfix due date
- Plan authority control testing document
- Review Orchid state (second week of Sprint)
- Start
ARCH-30
-
Getting issue details...
STATUS
| - Dec 9 - Notify community regarding sharing information of new modules
|
155 | | - 12/12/2022 - Nolana GA
- Complete
ARCH-30
-
Getting issue details...
STATUS
| - Dec 23 - Deadline for requests to add new modules to the reference environments
|
156 | | - Create ticket for Kitfox for UAT
| |
157 | | - Authority control UAT (mid release)
- Search UAT (mid release)
- Wrap up Authority control work for Orchid
- Poppy features defined
- Conduct or create user stories for performance/load testing. See Types of tests
| - Holidays
- Jan 27 - Deadline for acceptance of new modules by Technical Council
|
158 | | - Review MG/Nolana issues add user stories as applicable
- Prepare data for Bugfest
- Create user stories for Kitfox that outline your needs and instructions
- FWIW - I think settings needs to be cleaned
- Please consider how to test long lists/tables
| - Jan 30 - Bugfest environment preparation kick-off
- Feb 10 - Modules feature development freeze R1 2023 - Platform complete modules
|
159 | | - Migration testing
- Team defines checklist
- Meeting with Folijet and Kitfox to discuss bugfest
Add release notes - Include any previous release notes that still relate to the release
- flag any known items with the label known-issue-<<release>>
Accessibility Testing | |
160 | | Team - review modules readiness for release. Team - Bugfest smoke testing | - Release integration week
- Deployment to Orchid bugfest env is completed
- Mar 6 -17 Bugfest testing
|
161 | |
| Mar 6 -17 Bugfest testing |
162 | | Start Poppy development | Mar 31 - Bugfest fix releases |
163 | |
| Apr 10 - Release is public |