Gap Analysis Meeting 2018-06-13
Attendees
Cate, Harry, Holly, Mark
Notes
Reviewed draft spreadsheet https://docs.google.com/spreadsheets/d/1GbQQ5ABuYE_NpBIR3KrNj-KEwEkirUZ_K1th4PnHxA8/edit#gid=1934589045
Decided to remove some epics, such as Testing, Migration tools, UX overhead, Operations, Performance, Reporting, etc. These are tasks that will be completed and don't need to be prioritized.
Changed "needed by" drop-down options to be clearer
go-live
can wait until Fiscal year rollover
can wait - up to a quarter after go-live
can wait - up to 1 year
NOT NEEDED
Will add epics that don't have features so that everything is included.
Action Items
Updated next steps:
All UXPROD issues entered by COB June 13–PLANNED TO BE COMPLETED TODAY
In meantime, Mark will work on format of spreadsheet for early implementers–FINAL COMMENTS GIVEN TO MARK TODAY
This group will review spreadsheet Tuesday before PC meeting–MET ON JUNE 13
Holly will create instructions for spreadsheet
Cate will add UXPROD issues for epics that don't have features
Show sample spreadsheet to Product Council on June 14
This group walks through Cornell example at meeting on June 15
Assign spreadsheet to one person at each early implementer site (PC person if available) on June 18
Spreadsheet from early implementers due on June 22
Then need to ask for estimates on any UXPROD without them and updates for UXPROD issues with old estimates