Roadmap
EPICS
Release preparation
Modules release
Timeline
Sprint | Dates | Dates | Name | Description |
---|---|---|---|---|
Sprint 97 | 14 September 2020 | API freeze for platform (Okapi/Stripes/RMB) readiness review | RC review released platform components and facilitate meeting with unreleased components owners to discuss available impediments/issues/problems to understand when component could be released | |
18 September 2020 | API freeze for platform (Okapi/Stripes/RMB) | API freeze for platform (Okapi/Stripes/RMB) and deadline for initial releases of platform components. No breaking changes to the platform after this date. | ||
Sprint 98 | 21 September - 2 October 2020 | Teams upgrade to the platform components | Teams upgrade to the platform components versions that were released. | |
25 September 2020 | Major interface version provided to be updated | |||
28 September – 2 October 2020 | Schema upgrade testing week (BE core modules) | |||
2 October 2020 | Review upgrade to platform components status. | RC review upgraded components and facilitate meeting with non-upgraded components owners to discuss available impediments/issues/problems to understand when component could be upgraded | ||
Sprint 99 | 5 October - 16 October 2020 | Teams modules releases | ||
Platform Core Back End (Storage) modules releases | 2-3 days | |||
Platform Core Back End (Business logic) modules releases | 2-3 days | |||
Platform Core Front End modules releases | 2-3 days | |||
Storage module releases | 2-3 days | |||
Platform complete BE modules releases | 2-3 days | |||
Platform complete Front End modules releases | 2-3 days | |||
25 September 2020 | Modules feature development code freeze Q3 2020 - Platform core modules | |||
2 October 2020 | Modules feature development code freeze Q3 2020 - Platform complete modules | |||
12 October 2020 (Monday) | Review modules release readiness | RC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released). Major interface version provided to be updated | ||
12 October 2020 | Platform core modules release (FE core modules) | |||
12 October – 16 October 2020 (Oct5-Oct 9) | Schema upgrade testing week | Major modules versions should be released. Schema upgrade have to be released and tested locally by each team. | ||
16 October 2020 | Schema upgrade testing review | RC review upgraded modules and facilitate meeting with non-upgraded modules owners to discuss available impediments/issues/problems to understand when schema could be upgraded. | ||
16 October 2020 | Final Review modules release readiness | RC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released | ||
Module release deadline | All modules must see Q3-compatible releases by this date | |||
Sprint 100 | 21 October 2020 | Contact with devops | Review release information. Up to date versions should be set | |
19 October- 23 October 2020 | Release integration week | Bugfest environment preparation, testing of schema and data migration by EBSCO FSE team | ||
26 October - 13 November 2020 | Q3 Release testing and hardening period | |||
26 October - 30 October 2020 | Functional testing (Bug Fest) | Execute all TestRail test cases | ||
Sprint 101 | 26 October - 6 November 2020 | Performance testing | ||
2 November - 13 November 2020 | Ongoing triage and bug fixing of bugs begins immediately | |||
10 November 2020 | Bugfix releases readiness | RC review bugfix dashboard and facilitate meeting with unresolved modules owners to discuss available impediments/issues/problems to understand when module could be released | ||
13 November 2020 | Bugfix releases deadline | |||
Sprint 102 | 23 November 2020 | Release is public |