Release Management Stakeholder group
Attendees
Mark Veksler Debra Howell Lee Braginsky Mike Gorrell Kristin Martin Khalilah Gambrell Yogesh Kumar
https://openlibraryfoundation.zoom.us/j/88356244681?pwd=aFo1cEhVam1ENTN1ZHFOZWg0V1Jxdz09
Meeting Time: 8:30 AM Eastern Time
Discussion items
Time reserved | Description | Presenter | Details/Comments |
5 min | Intros | all | |
5 min | Poppy release skipping | all | Desire to skip Poppy and merge with Quesnelia: Khalilah presents proposal. Benefits:
Questions: are there any features that any library is waiting on with urgency? Not sure any exist. People will want reassurance that all features for Poppy/Quesnelia are included in the later pushed release. Positive: we gain two additional sprints by revising the timeline. What we want to avoid: painful Bugfest experience. Yogesh is working to improve the quality of our releases. Kristin/Debra support an intensive focus on Data Import (P1/P2), but this will not fix everything. General Release date: November 20, 2023 Yogesh: new steps in quality assurance. Early testing within the sprint. Split sprint into 70% development time, 30% testing/hardening time. Also running automated tests as soon as code is merged in. Both steps should help reduce late-breaking bugs |
5 min | CSP requests review | all | Approved on Slack |
15 min | Any other business |