Sprint Goal / Focus
- Bug Fixes
- Document filters
Sprint Schedule
- Sprint: 177
- Start Mon 23 Oct 2023
- Finish Fri 3 Nov
- Sprint Board
- Jira Sprint: 1990
- Sprint Report
- Release: 2024.1 Quesnalia
Sprint 17 of 17 since Release Development Cycle Starts (Sprint 176) to Feature Freeze (Sprint 175: 6 Oct 2023)- Sprint 187: Module Release Deadline (22 Mar 2024) [
FOLREL-565] - Sprint 189: Bugfix Release Deadline (19 Apr 2024) [
FOLREL-581]
Development Meetings
- Wed 25 Oct
- Mon 30 Oct
- Wed 1 Nov
Sprint Capacity
Team Availability: Schedule | Calendar
Notes / Exceptions:
- Ethan 9-17 Oct
Lead Roles:
- Code Review: ...
- QA: Owen Stephens
QA Environment:
- folio-snapshot, folio-snapshot-2
Present
Planning Questions
- Does the issue meet the criteria for Definition of Ready?
- What front and back end components are affected?
- What changes need to be made? (additions, removals or modifications)
- What development tests need to be written?
- What data does the developer need to verify their work?
- What are the known unknowns?
- What is needed to QA? (environment, data, scripts)
Navigation
Sprint Planning
- not in sprint
or @ - in sprint
- not ready
- pending triage / planning
Sprint Focus
No Feature
Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|
Tests
Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|
NA |
Release Tasks (Poppy Release)
Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|
NA |
Release Tasks (Non-Flower Release)
Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|
Maintenance
Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|
Changes
Added
Removed: note whether rescheduled or deferred
Feature ID | Issue ID | Change | Notes |
---|---|---|---|
Rolled Over From Previous Sprint
Planning Notes Template
- Current State
- TODO
- Development Estimate
In Development
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
Code Review | |||
- ERM-2836Getting issue details... STATUS | |||
- ERM-3056Getting issue details... STATUS | |||
Claudia Malzer | |||
Sprint Backlog
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
Blocked
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
NA | |||
In QA
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
For Elaboration
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
For Release Prep / Pending Testrails
Cross-check against e2e Jira issues
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|
Bugfix Cycle
Feature ID | Issue ID | Sprint Backlog? | Notes / Estimates / Actions |
---|---|---|---|