Capture/document the ad-hoc process which we've been following in lieu of a having a formally defined process
Go back to the previous meeting notes and try to resurrect the process we started to define (see link to meeting notes above)
Do #1 now (short-term/stop-gap solution) and continue to try to make progress on #2 (longer-term solution)
Considerations
Relevant release milestones
Expectations for the TCR process / Which list should we be looking at?
How do we ensure this isn't a moving target for developers (both internal and external to the project) throughout the release cycle
Do we need notification mechanisms for announcing changes to the OST list for the release in development?
Implications on planning for the next release cycle
Notes from today :
Focus on upkeep:
How do statuses transition?
What is active?
Can be up to 4 releases
Right now - Poppy, Orchid, Nolana. But Q is also "being developed" Or is it up to GA?
Period of time where there is often 2 in dev. We wouldn't want to make Q have to comply with P
What milestones should inform statuses? Where in the dev process can we nail things down? Statuses in line with dev processes?
Milestones are in the release cycle but toward the end. Don't know until part way through the release cycle what version of RMB, etc
Maybe changes need to be valid all the way down to active
Changes happen right up to the last moment, and even during support periods
Want to be able to make the decisions we can early but that won't be all of them
Accepted would be nice but maybe not practical, too linear. Leave for now.
Do the kinds of changes matter? Like only for security vs for features
Discuss more later
If we accept changes all along does the page make sense at all? Can people still use it for planning if it is always a moving target?
Maybe for active only take security changes? But basic technologies stay the same
Freeze earlier in the cycle? Tell people early on if the version will change, like what Stripes does, RMB process is different? Stripes bumps version number early on then aggregates changes in the cycle to that release.
Ahead of cycle determine okapi/stripes/rmb versions?
Making decision on stuff we own different from external
Have to plan far ahead
Lists was Orchid version of stripes but it was going to be in Poppy. If new modules have to have released versions and next version will have a breaking change, they have to refactor
So if know going to break stripes do early in the cycle but then can they use snapshot versions?
challenge to say they have to use version that doesn't exist yet
snapshot versions interferes with reproducible builds
Distinguish between internal released tools and external ones?
Limit OST to things not internal?
Might be easier to talk about external separate from internal?
Historical policy around 1st party releases, could be talked about in the future
Ended up updating change column to clarify what can/is likely to change in statuses
Probably difficult to change release process so this makes sense to distinguish, but doesn't really help TCR problem
Might need to relax OST restrictions for 1st party items
Do we still need accepted?
Might make sense for third party
Need to see if actually works practically and then come back to it maybe
Upkeep activities
Drafting starts at GA for release that is two releases later (R starts at GA of P)
Move to accepted before release scope refinement deadline for given release
Move to active when development begins on that release, which is around time of feature freeze of the release prior to the given release
Archived when it is out of support, tied to GA of future release (2 out?)
TC should plan when the release schedule is published