- Finalize features scope
Action |
| Responsible | Sprint | Notes |
---|
- Update Features' statuses
- Identify which features are at risk and the "at-risk" label to the feature.
|
| Product owner |
|
|
All user stories tied to features should be written and estimated. |
| Product owner |
|
|
Testing - Identify remaining Karate tests to complete for the module release
- Identify automated e2e test cases to complete by start of bugfest
- Identify the cases in our functionality consumed by other modules and create test for functionality collaboration
|
| Team |
|
|
Conduct user acceptance testing |
| - Product owner (maybe a SIG member can help write tasks?)
- Team needs to setup an environment for UAT
|
| Likely to begin during the week of 02.13 |
Conduct or create user stories for performance/load testing. See Types of tests |
| Team |
| Haven't done this yet |
One sprint before feature freeze
Action | Responsible | Sprint | Notes |
---|
- Update Features' statuses
- Identify which features are at risk and the "at-risk" label to the feature.
| Product Owner |
|
|
- Test rails: Write/Review test cases
- Please consider how to test long lists/tables
| Product Owner/Manual QA/SIG |
| Mainly to account for boundary conditions. Ideal to have this as part of the user story |
- Prepare data for Bugfest
- Create user stories for Kitfox that outline your needs and instructions
- FWIW - I think settings needs to be cleaned
- Please consider how to test long lists/tables
| Team |
| On track. 1/ Need to leave authority record from Nolana as is. Khalilah will send instructions to Kitfox. 2. Once the env is ready, Khallah and Valeri will prep the data for testing |
- Add release notes
- Include any previous release notes that still relate to the release
- flag any known items with the label known-issue-<<release>>
| Team |
| Developer facing - Team Consumer facing - Khalilah + Team E.g. Nolana (R3 2022) Release Notes |
Accessibility Testing | Team |
|
|
- Conduct or create user stories for performance/load testing. See
Types of tests | Team |
|
|
Bugfest (aka Business Acceptance Testing) period
Action | Responsible | Sprint | Notes |
---|
- Update Features' statuses
- Identify which features are at risk and the "at-risk" label to the feature.
| Product Owner |
|
|
- User stories: update Release field for those stories/bugs/tasks/etc that will not be done for the release.
| Product Owner |
|
|
- Add release notes
- Include any previous release notes that still relate to the release
- flag any known items with the label known-issue-<<release>>
| Team |
|
|
Team's accept Bugfest build. - Teams must conduct smoke tests to verify key functionality works as expected BEFORE Bugfest is made available to community
- Teams must document
- App/module not ready for testing
- Issues yet to be resolved
| Team |
|
|
- Conduct performance/load testing. See
Types of tests | Team |
|
|
Sprint before GO-Live
Action | Responsible | Sprint |
---|
- Update Features' statuses
- There should be no at-risk features
| Team |
|
- User stories: update Release field for those stories/bugs/tasks/etc that will not be done for the release.
| Product Owner |
|
- Add/Review release notes
- Include any previous release notes that still relate to the release
- flag any known items with the label known-issue-<<release>>
| Team |
|
- Complete remaining performance/load testing. See
Types of tests | Team/PTF |
|
Go-Live sprint
Action | Responsible | Sprint |
---|
Teams must conduct smoke tests to verify key functionality works as expected | Team |
|
Testing: All Karate tests and e2e tied to release functionality should be done and running | Team |
|
- Add/Review release notes
- Include any previous release notes that still relate to the release
- flag any known items with the label known-issue-<<release>>
| Team |
|