Release Readiness Checklist - Nolana

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Current »

Two sprints before feature freeze 

ActionResponsible
  • Update Features' statuses
  • Identify which features are at risk and the "at-risk" label to the feature.  
Product owner

All user stories tied to features should be written and estimated. 

Product owner

Testing

  • Identify features that require e2e tests 
  • Identify features that require Karate tests
Team
Conduct user acceptance testing 
  • Product owner (maybe a SIG member can help write tasks?) 
  • Team needs to setup an environment for UAT
Conduct or create user stories for performance/load testing. See Types of testsTeam

One sprint before feature freeze 

ActionResponsible
  • Update Features' statuses
  • Identify which features are at risk and the "at-risk" label to the feature.  
Product Owner
  • Test rails: Write/Review test cases 
    • Please consider how to test long lists/tables 
Product Owner/Manual QA/SIG
  • Prepare data for Bugfest
    • Create user stories for Kitfox that outline your needs and instructions 
      • FWIW - I think settings needs to be cleaned
    • Please consider how to test long lists/tables 
Team
  • Add release notes 
    • Include any previous release notes that still relate to the release 
    • flag any known items with the label  known-issue-<<release>>
Team

Accessibility Testing

Team
  • Conduct or create user stories for performance/load testing. See
Types of tests
Team

Bugfest (aka Business Acceptance Testing) period 

ActionResponsible
  • Update Features' statuses
  • Identify which features are at risk and the "at-risk" label to the feature.
Product Owner
  • User stories: update Release field for those stories/bugs/tasks/etc that will not be done for the release. 
Product Owner
  • Add release notes 
    • Include any previous release notes that still relate to the release 
    • flag any known items with the label  known-issue-<<release>>
Team

Team's accept Bugfest build. 

  • Teams must conduct smoke tests to verify key functionality works as expected BEFORE Bugfest is made available to community 
  • Teams must document 
    • App/module not ready for testing 
    • Issues yet to be resolved
Team
  • Conduct performance/load testing. See
Types of tests
Team

Sprint before GO-Live 

ActionResponsible
  • Update Features' statuses
  • There should be no at-risk features
Team
  • User stories: update Release field for those stories/bugs/tasks/etc that will not be done for the release. 
Product Owner
  • Add/Review release notes 
    • Include any previous release notes that still relate to the release 
    • flag any known items with the label  known-issue-<<release>>
Team
  • Complete remaining performance/load testing. See
Types of tests
Team/PTF

Go-Live sprint

ActionResponsible
Teams must conduct smoke tests to verify key functionality works as expectedTeam

Testing: All Karate tests and e2e tied to release functionality should be done and running 

Team
  • Add/Review release notes 
    • Include any previous release notes that still relate to the release 
    • flag any known items with the label  known-issue-<<release>>
Team