Our goal was to test Q4 release in the similar fashion as a customer would conduct UAT. We wanted to see if our current development/engineering process can provide desired quality level. Bug Fest was very useful experience for the FOLIO team. We realized that we need to improve quality gates that we have in place and to be build additional layers of tests integrated into our continuous integration pipeline. We are planning to address technical debt and complete significant amount of quality improvement work in Q1 and the following quarters. It will allow us to get improved results for future releases.
It was the first time we attempted to execute such an extensive manual product test run. That being said, it went relatively smooth for the first try:
There were relatively few questions about the process in the bug-fest Slack channel at the beginning of the week.
Participants did't require a lot of support in following the directions for Bug Fest.
We incurred one performance issue on Tuesday that blocked all the testing activities. It was quickly resolved by Hongwei.
We were not able to execute all test tasks in the first 2 days and event had to be extended for another 3 days.