Skip to end of banner
Go to start of banner

2022-09-28 Product Owner Meetings

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 5 Next »


































 

Attendees:  Khalilah Gambrell 

 TopicsTimePresenterAgenda/Notes
Announcements 10 minutes 

All 

Upcoming conferences

Prioritization status: Critical Path (e-2-e tests) prioritization  5 minutes

All 

  • AQA team have begun to automated critical path test cases.
  • Action item for POs: Review your test cases in Test rails
    • Prioritize in Test rails
    • Confirm which test cases should be Critical path
    • Set Priority for those Critical path tests

Deadline: Review and priority by the end of Sprint 149

Have questions, please contact Anton Emelianov (Deactivated) and/or Lee Braginsky 

Morning Glory Release

  1. Morning Glory has been released! 
        1. Reminder: Update Release Notes - Morning Glory (R2 2022) Release Notes
          1. To have an known issue added to the Bugfest and Release Notes table, please add the label known-issue-morningglory. An issue will be removed from the list once the issue is Closed 
        2. Retro Morning Glory R2 2022 retrospective Feel free to add your thoughts to board - https://easyretro.io/publicboard/RFFDjTYZnVUVqdRYEhmBSNzS6mJ2/d2598b93-4c67-4c15-87dc-2e8fd1c5cfe8
          1. Date: Wednesday, October 5 at 10am ET - 12:00pm ET Link: https://zoom.us/j/457757515
Nolana Release - Key dates

Key Stats to review:

NOTE: Only one sprint left for new development. Please update status, release, and/or split feature. If a feature is a MUST for Nolana and it is at-risk, please add the label nolana-at-risk to the feature. 

Nolana - no change in release date (December 12)

    1. Sprint 149: September 30 - Deadline for TC to accept new modules. 
    2. Sprint 150
      1. New Development Freeze  - Core (October 7) 
      2. New Development Freeze  - Complete (October 14)  
      3. Sprint 150-2 
        1. Nolana release hardening (initial) 
    3. Sprint 152 - Bugfest
Orchid Features Refinement 

  1. Sprint 150: Orchid scope finalized (proposed date October 10)
    1. Features defined and reviewed with team 
    2. Development estimates complete 
  2. Sprint 152: Orchid new development officially begins [October 31 (based on module release deadline)]... but can start before...


  • No labels