Welcome to Sprint 130!
Plans for this sprint
- Finish log4j updates for Juniper the first week of the sprint (before holidays).
- Work on log4j updates for Kiwi. <==Won't be finished until after holidays!
- Work on log4j updates for Iris. <==Won't be finished until after holidays!
- Fix P1/P2 bugs found in Juniper/Kiwi releases.
- Finish JIRA tickets carried over from Sprint 129.
- Work on critical "tech debt" issues (such as testing).
Plans for the Lotus (R1 2022) release
- Fix critical bugs.
- Address "Tech debt" issues (such as testing).
- Work on Inventory features listed below.
Features planned for Lotus (R1 2022) release
- UXPROD-2867 (Add Administrative note to Instance, Holdings, and Items) <==In-progress–back-end story IN REVIEW and 3 front-end stories are OPEN!
- UXPROD-3430 (Inventory. Implement Facets on filtering (Instance, Holdings, Item) when using Elasticsearch) <==In-progress–final story is IN REVIEW!
- UXPROD-3033 (Support Custom Fields Searching in Users) <==Added recently–only one front-end user story!
- UXPROD-1892 (Instance: Add related instances data element) <==Will be ready for grooming 12/20–three small stories!
- UXPROD-2703 (nventory. Result list. Refined display rules MCL. Adding publication date) <==Only one small story–is part of Sprint 130!