Sprint DatesSprint GoalsRelease related milestone(s)
151

-  

  • Stabiilize eholdings export 
  • authority control development
Release Nolana modules
152

-

  • Complete SPIKE  ARCH-22 - Getting issue details... STATUS
  • Stabilize eholdings export for Nolana release or make the decision to move it to Orchid
  • authority control development
Nolana bugfest
153

-

  • Nolana bugfest bugs 
  • authority control development begin (reporting SPIKE) 
  • Start ARCH-36 - Getting issue details... STATUS
  • MG HF # 1 module release date FNA 11/21 | New date TBD

154

-

  • MG HF # 1 release date to public FNA 11/28 | New date TBD 
  • Complete  ARCH-36 - Getting issue details... STATUS
  • 12/02/2022 - Nolana Bugfix due date 
  •  Plan authority control testing document
  • Review Orchid state (second week of Sprint) 
  • Start ARCH-30 - Getting issue details... STATUS  
  • Dec 9 - Notify community regarding sharing information of new modules
155

-

  • 12/12/2022 - Nolana GA
  • Complete ARCH-30 - Getting issue details... STATUS  
  • Dec 23 - Deadline for requests to add new modules to the reference environments
156

-

  • Authority control UAT (mid release) 
  • Holidays 
157

-

  • Authority control UAT (mid release) 
  • Poppy features defined
  • Conduct or create user stories for performance/load testing. See Types of tests
  • Holidays
  • Jan 27 - Deadline for acceptance of new modules by Technical Council
158

-

  • Prepare data for Bugfest
    • Create user stories for Kitfox that outline your needs and instructions 
      • FWIW - I think settings needs to be cleaned
    • Please consider how to test long lists/tables 
  • Jan 30 - Bugfest environment preparation kick-off
  • Feb 10 - Modules feature development freeze R1 2023 - Platform complete modules
159

-

Add release notes 

    • Include any previous release notes that still relate to the release 
    • flag any known items with the label  known-issue-<<release>>

Accessibility Testing

  • Feb 24 - module releases
160

-

Team - review modules readiness for release. 
  • Release integration week
  • Deployment to Orchid bugfest env is completed
  • Mar 6 -17 Bugfest testing
161

-


Mar 6 -17 Bugfest testing
162

-

Start Poppy developmentMar 31 - Bugfest fix releases
163

-


Apr 10 - Release is public