To have an known issue added to the Bugfest and Release Notes table, please add the labelknown-issue-morningglory. An issue will be removed from the list once the issue is Closed
NOTE: Only one sprint left for new development. Please update status, release, and/or split feature. If a feature is a MUST for Nolana and it is at-risk, please add the label nolana-at-risk to the feature.
Nolana - no change in release date (December 12)
Sprint 149: September 30 - Deadline for TC to accept new modules.
Sprint 150
New Development Freeze - Core (October 7)
New Development Freeze - Complete (October 14)
Sprint 150-2
Nolana release hardening (initial)
Sprint 152 - Bugfest
Orchid Features Refinement
Sprint 150: Orchid scope finalized (proposed date October 10)
Features defined and reviewed with team
Development estimates complete
Sprint 152: Orchid new development officially begins [October 31 (based on module release deadline)]... but can start before...