Action Plan | Notes |
---|---|
Sprint 32-34 | |
Agreed not to point stories during grooming meeting. BE or FE team point groomed stories later separately. | |
Anna Melnyk to send Darcy an example of video demo from Cate. | done |
In order to make standups shorter agreed: - anyone who is not interested in standup's demos could skip them. - back to this question again after onboarded people leave the team. | |
The team to provide a feedback about stories' description. | |
Sprint 27-29 | |
BE devs to investigate and describe all technical details for BE stories before taking in work (not just a copy-past of initial story). | |
Sprint 24-26 | |
Agreed to change Tester Assignee for tickets which are waiting for review for more than 3 days. | |
Sprint 21-23 | |
To organize a separate meeting for spike discussion with PO, Folio Tech Lead and Vega team before estimating and taking a Spike to sprint. | |
Sprint 18-20 retro | |
no action items | |
Sprint 15-17 Retro | |
Tetyana Afanasyeva to organize a meeting with Core team in order to resolve blockers if any. | done |
PO to provide with expected result and use cases for spikes. | |
Khalilah Gambrell to discuss upcoming features with other POs in order to add UI stories in the backlog; pull in stripes-related work; pull in UI defects. | |
Sprint 11-14 Retro | |
Maxim Didenko and Kostyantyn Khodarev to consider what can be added to tech debt backlog | done: nothing to be added |
Sprint 9-10 Retro | |
Maxim Didenko to create Tech Debt story | done |
Tetyana Afanasyeva to discuss a separate environment for release candidate review on SoS meeting | done |
Devs to add video capture for bugs presentation to POs | |
Revisit DoD to ensure we are aligned. | done |
General
Content
Integrations