Table of Contents

Roadmap

Image Removedimage2024-2-25_18-58-47.pngImage Added

EPICS

Release preparation

Jira Legacy
serverSystem JIRAFOLIO Issue Tracker
columnIdsissuekey,summary,issuetype,duedate,status
columnskey,summary,type,due,status
maximumIssues20
jqlQueryproject in (Folrel, FOLIO) and type=epic and summary ~ "R1 2024" and summary !~ "release" order by key
serverId01505d016ccf3fe4-b8533301-3c2e368a-90f1983e-ee9b165564fc20c466b11a49

Modules release

Jira Legacy
serverSystem JIRAFOLIO Issue Tracker
columnIdsissuekey,summary,issuetype,duedate,status
columnskey,summary,type,due,status
maximumIssues20
jqlQueryproject = Folrel and type=epic and summary ~ "R1 2024" and summary ~ "release" Order by key
serverId01505d016ccf3fe4-b8533301-3c2e368a-90f1983e-ee9b165564fc20c466b11a49

Timeline

18801 Apr 23 Apr
SprintDatesDatesNameDescription
Sprint 182196

19 Jan  

Notify community regarding sharing information of new modulesInclude module to FOLIO Module/JIRA project-Team-PO-Dev Lead responsibility matrix
Sprint 183197

02 Feb  

Deadline for requests to add new modules to the reference environments

Create Jira ticket at FOLIO Jira project ex. 

Jira Legacy
serverSystem JIRAFOLIO Issue Tracker
columnIdsissuekey,summary,issuetype,created,updated,duedate,assignee,reporter,priority,status,resolution
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId01505d016ccf3fe4-b8533301-3c2e368a-90f1983e-ee9b165564fc20c466b11a49
keyFOLIO-3255

Sprint 184198

16 Feb  

Ramsons R2 2024 Sunflower R1 2025 release scope composition deadlineLead PO prepared list of features for Ramsons R2 2024 Sunflower R1 2025 release and input from SIGs
Sprint 185199

26 Feb  

API freeze for platform (Okapi/Stripes/RMB/Spring) readiness reviewRC review released platform components and facilitate meeting with unreleased components owners to discuss available impediments/issues/problems to understand when component could be released

01 Mar  

API freeze for platform (Okapi/Stripes/RMB/Spring)

Okapi/Stripes/RMB/SpringWay freeze and deadline for initial releases of platform components. 

No breaking changes to the platform after this date.

Feature development freeze for R1 R2 2024 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R1 R2 2024 period. Separate release branch has to be created after feature freeze date. All R1 R2 2024 bug fixed have to be applied to both release and Master branches. Next R3 2023 R1 2025 release period feature development is expected on Master branch.

Features test cases preparation deadlineTo start test case automation for Poppy features test cases need to be prepared.
Deadline for acceptance of new modules by Technical Council at Poppy Ramsons (R1 R2 2024)New Module Technical Evaluations - Technical Council - FOLIO Wiki
Sprint 186200

04 Mar 15 Mar  

Teams upgrade to the platform componentsTeams upgrade to the platform components versions that were released.

04 Mar

Bugfest environment preparation kick-off

Conduct meeting for review Bugfest preparation plan

Create appropriate jira tickets in Kitfox backlog

Review list of new modules

Review data cleanup

Review new data

07 Mar -08 Mar  

Ramsons Sunflower release scope decomposition and estimation

11 Mar  

Ramsons R2 2024 Sunflower R1 2025 release scope refinement deadline

POs prepare list of UXPROD features aligned with Ramsons R2 2024 team Sunflower R1 2025 team capacity. PO present prepared scope at next PO Weekly meeting at <TBD>

15 Mar


Major interface version provided to be updated
Review upgrade to platform components status.RC review upgraded components and facilitate meeting with non-upgraded components owners to discuss available impediments/issues/problems to understand when component could be upgraded
Modules feature development freeze R1 R2 2024Feature development freeze for R1 R2 2024 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R1 R2 2024 period. Separate release branch has to be created after feature freeze date. All R1 R2 2024 bug fixed have to be applied to both release and Master branches. Next R1 2024 2025 release period feature development is expected on Master branch.
Quesnelia R1 Ramsons R2 2024 features acceptance deadline

Sprint 187201

18 Mar 22 Mar  

Schema upgrade testingMajor modules versions should be released. Schema upgrade have to be released and tested locally by each team.

18 Mar 22 Mar  

Teams modules releases

28 Mar   (Thursday)

Modules release readiness reviewRC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released). Major interface version provided to be updated

18 Mar  

New blank Poppy bugfest environment is prepared 

20 Mar  

Scripts are ready for new modules deployment

21 Mar  

Schema upgrade testing reviewRC review upgraded modules and facilitate meeting with non-upgraded  modules owners to discuss available impediments/issues/problems to understand when schema could be upgraded.

22 Mar  

Final Review modules release readiness

RC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released
Module release deadlineAll modules must have R1 2024-compatible releases by this date
Finalize release notes for Poppy features/applications/modules Release notes have to be updated

25 Mar  

Contact with Kitfox/FSE devopsReview release information. Up to date versions should be set

25 Mar 29 Mar  

Release integration weekBugfest environment preparation, testing of schema and data migration by Kitfox/FSE team

27 Mar  

Deployment to Poppy bugfest env is completed.

Data set is ready


28 Mar 29 Mar  

Sanity testing at Poppy bugfest env

Sprint

202-203

19 Apr  

R1 R2 2024 Release testing and hardening period

01 Apr 12 Apr  

Functional testing (Bug Fest)Execute all TestRail test cases

01 Apr 12 Apr  

Performance testing

Sprint 189

15 Apr 19 Apr  

Ongoing triage and bug fixing of bugs begins immediately

18 Apr  


Bugfix releases readinessRC review bugfix dashboard and facilitate meeting with unresolved modules owners to discuss available impediments/issues/problems to understand when module could be released
Create R1R2-2024 platform complete release branch

TBD

19 Apr  

Bugfix releases deadline

Sprint 204

25 Apr

Final Smoke testing
Sprint 190

29 Apr  

Release is public


Modules planned for release


Release notes

Ramsons (R2 2024)TBD - Release Notes

...