Sprint | Dates | Dates | Name | Description |
---|---|---|---|---|
Sprint 1xx | 01 Feb | API freeze for platform (Okapi/Stripes/RMB) readiness review | RC review released platform components and facilitate meeting with unreleased components owners to discuss available impediments/issues/problems to understand when component could be released | |
05 Feb | API freeze for platform (Okapi/Stripes/RMB) | API freeze for platform (Okapi/Stripes/RMB) and deadline for initial releases of platform components. No breaking changes to the platform after this date. | ||
Sprint 1xx | 08 Feb - 05 Mar | Teams upgrade to the platform components | Teams upgrade to the platform components versions that were released. | |
Sprint 1xx | 26 Feb | Major interface version provided to be updated | ||
Modules feature development freeze R1 2021 - Platform core modules | ||||
Sprint 1xx | 01 Mar -05 Mar | Schema upgrade testing week (BE core modules) | ||
05 Mar | Review upgrade to platform components status. | RC review upgraded components and facilitate meeting with non-upgraded components owners to discuss available impediments/issues/problems to understand when component could be upgraded | ||
Modules feature development freeze R1 2021 - Platform complete modules | ||||
08 Mar - 12 Mar | Schema upgrade testing week | Major modules versions should be released. Schema upgrade have to be released and tested locally by each team. | ||
08 Mar - 19 Mar | Teams modules releases | |||
09 Mar - 10 Mar | Platform Core Back End (Storage) modules releases | |||
10 Mar - 11 Mar | Platform Core Back End (Business logic) modules releases | |||
11 Mar - 12 Mar | Platform Core Front End modules releases | |||
Platform Complete Back End (Storage) modules releases | ||||
Sprint 1xx | 15 Mar - 17 Mar | Platform complete BE (Business logic) modules releases | ||
17 Mar - 19 Mar | Platform complete Front End modules releases | |||
15 Mar (Monday) | Modules release readiness review | RC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released). Major interface version provided to be updated | ||
19 Mar | Schema upgrade testing review | RC review upgraded modules and facilitate meeting with non-upgraded modules owners to discuss available impediments/issues/problems to understand when schema could be upgraded. | ||
19 Mar | Final Review modules release readiness | RC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released | ||
Module release deadline | All modules must see R1R2-compatible releases by this date | |||
22 Mar | Contact with devops | Review release information. Up to date versions should be set | ||
22 Mar - 26 Mar | Release integration week | Bugfest environment preparation, testing of schema and data migration by EBSCO FSE team | ||
Sprint 1xx | 29 Mar - Apr | Q3 Release testing and hardening period | ||
29 Mar - Apr | Functional testing (Bug Fest) | Execute all TestRail test cases | ||
29 Mar - Apr | Performance testing | |||
Sprint 1xx | Apr - Apr | Ongoing triage and bug fixing of bugs begins immediately | ||
Apr | Bugfix releases readiness | RC review bugfix dashboard and facilitate meeting with unresolved modules owners to discuss available impediments/issues/problems to understand when module could be released | ||
30 | Bugfix releases deadline | |||
Sprint 1xx |
| Release is public |
...