2019-01-0814 | Cate Boerema (Deactivated) - Critical path diagram for Q1 Circulation Features across Vega and Core teams can be found here: https://drive.google.com/drive/folders/1j4UuMl6bURkmslsKlVK_NlaY83H9Tr6-
- Issues:
- Does not account for work needed to factor time zone into due date/time calculations
- April 8 release date does not leave sufficient time to complete features. Can/should we push the release date from April 8 - April 19th?
- No bandwidth for 4 high priority Inventory features (UXPROD-1397, UXPROD-1396, UXPROD-1303, UXPROD-149) which are needed to support Batch Import features Chalmers needed for "go-live"
- Risks:
- Many interdependencies
- New teams and processes (esp Core: Functional)
- High-level estimates
- Core: Functional Team kickoff planning underway - Oleksiy, Jakub, Vicoria, Cate and Marc Johnson met today to work through slide deck. Goal is to follow agile best practices adopted elsewhere on FOLIO.
- Overall Q1 Planning:
Jakub Skoczen Last week of sprint 54 (last sprint of Q4) Functional work items update: - Already started working on some Q1 issues (usually UI-only, Michal, Aditya, Zak)
Q4 Release Management updates: - We are working on a new release for ui-users to include bugfixes done by UNAM. We need a new minor release because of the way the bugfixes was provided (only on a master branch, not on a release branch)
- A new bugfix release for mod-permissions is going to be released later today and it will include a fix to the caching issue that seem to downgrade backend performance across many backend modules (MODAT-42)
- Q4 Release Management: all modules, interfaces (APIs) and their Q4 versions are tracked in this spreadsheet (updated at real-time):
https://docs.google.com/spreadsheets/d/1m966Ch822PUtsdvo01mS605ndB08ZhT7RRP3tnBRuX0/edit Q4 Release is going according to plan: https://docs.google.com/spreadsheets/d/1-4fMUyfnMhaMoJuEiwaABGu7ZzePvzhjya-nyV3dvvs/edit#gid=0
OKAPI/RMB, Performance NFRs Performance: MODINVSTOR-215, latest status from Julian is that the issue and new mod-inventory-storage release will be ready by Wednesday Starting from this week and intensifying next week core back-enders will focus on various performance issues (Adam, Julian, Jeremy, William). Heikki is going to be away until the end of the year. Nassib will act as a partial replacement.
- Other:Working on the new Core Teams structure and meeting schedule for Q1, starting with core:functional and following with core:platform.
Q4 RELEASED - User-facing release notes available here: Q4 2018 (Aster) Release Notes
| Jira Legacy |
---|
server | System Jira |
---|
jqlQuery | project = uxprod AND type = "new feature" AND (resolution not in (duplicate, "Won't Do") OR resolution is EMPTY) AND labels != NFR AND fixVersion was "Q4 2018" ON (2019-01-0814) ORDER BY cf[10002] ASC, assignee ASC, summary ASC |
---|
count | true |
---|
serverId | 01505d01-b853-3c2e-90f1-ee9b165564fc |
---|
|
| Jira Legacy |
---|
server | System Jira |
---|
jqlQuery | project = uxprod AND type = "new feature" AND (resolution not in (duplicate, "Won't Do") OR resolution is EMPTY) AND labels = NFR AND fixVersion was "Q4 2018" ON (2019-01-0814) ORDER BY cf[10002] ASC, assignee ASC, summary ASC |
---|
count | true |
---|
serverId | 01505d01-b853-3c2e-90f1-ee9b165564fc |
---|
|
|