Testing environment 2 – ECS (Question – do we need Testing Environment 2? Maybe just test scenarios with ECS environment?)
No fetch across all tenants > Ask several community members to test. Test duration: 1-2 days
Fetch in one tenant but not in central tenant. Ask several community members to test. Test duration: 1-2 days.
Ask FOLIO community administrators to update rules in at least one tenant and one is the central tenant.
Identify 1-3 libraries to participate. Testing this scenario will take about two weeks and my thought is that we ask libraries to reserve date/time and each library only has 1 day to setup rules and 2-3 days for user testing.
Need to assign a tenant for a community administrator to update and test with.
Test duration: Two Weeks. Give administrator 3-4 days to configure and remaining time for quickMARC testing.
...
Non-ECS environment
Testing > Customized bib and authority rules defined by Spitfire.
ECS environment
Ask FOLIO community administrators to update rules in at least one tenant and one is the central tenant. Test duration: One week
Need to assign a tenant for a community administrator to update and test with.
Following week – community members test these rules.
...
Only fetch MARC bib rules.
Only fetch MARC authority rules.
Anything else?