This page contains historical data from the Overall Status Update table on the FOLIO Q3 2019 (Daisy) Weekly Status Report

Report Date

Overall Status Update

Q1 Feature Count on Report Date



FunctionalNFR
2019-07-09

Jakub Skoczen

Cate Boerema (Deactivated)

  • All Core Functional must-haves for 3.1 are In review or In progress: https://issues.folio.org/secure/Dashboard.jspa?selectPageId=10628
  • Moving requests from one item to another is tracking for completion
  • Also making progress on Inventory cleanup (adding controlled vocabularies, notes etc.)
  • Fixing some critical Inventory search bugs with lots of help from Core Platform
  • Added release notes and stats from Q2: Release Notes
  • Capacity planning team working through process for MVP proposal
    • Have discussed assignment for POs (will share with them at PO meeting tomorrow)
    • Harry has put together a good deck on goals and process
  • SIGs continue to do re-ranking - lots of good discussions and many things are being considered lower priority than previously ranked.  Ranks are not always being updated in JIRA perhaps due to organizational process delays?

Getting issues...

Getting issues...

2019-07-02

Cate Boerema (Deactivated)

  • Q2 Clover release live as of yesterday!
  • Release notes and statistics will be available by end of week
  • Next big release is Q3 Daisy
    • Dashboard: https://issues.folio.org/secure/Dashboard.jspa?selectPageId=10627
    • Team plans are still being worked out, but each team has enough to get started
    • Q3 plans may evolve over the course of the quarter as we get the results of the SIG re-ranking exercise and with the capacity planning group's proposed plan for summer 2020
  • Next interim release is Q3.1
    • This is the release Chalmers will go live on
    • Module release deadline is July 24th, release is August 12
    • Anton has created a dashboard for bugs and we have extended to include the must-have features for the release, as well.  May also include the must-have stories.  
  • Capacity planning group meeting every couple of days with goal to have a plan for how the release proposal will be made prior to the stakeholder meeting
  • SIGs are working with POs to re-rank features.  Meetings I have attended so far have been really productive.
  • Core functional team:
    • Focus on the must-have bugs and features for Q3.1:
      • SIP2
      • Title level requests
      • Move requests from one item to another
    • Also working on Inventory cleanup:
      • Search bugs and enhancements - Charlotte is coordinating joint SME/Dev discussions on search to help identify the highest impact fixes.
      • Completing incomplete features in instance, holding and item
      • Niels Erik will be available on Core team full-time in July (apart from planned vacation)