Vega. Risks list.

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Current »

Risk probability
Risk impact
Probability levelDescriptionValueImpact valueImpact descriptionValue
Very lowIn past projects experience you have never seen this happen, but it probably could0.05Very LowSmall monetary loss or a few days of delay1
LowIt has happened on occasion0.25Low

Manageable monetary loss or a few weeks of delay

2
ModerateSometimes it happens and sometimes not

0.5

ModerateHeavy monetary loss or significant delay that doesn't endanger project success in general3
HighMost of the time this event happens0.75HighA loss or a delay that can endanger overall project success4
Very highIt has happened on almost every project and you think it always will but there is a chance of escape0.95Very highProject failure and possible additional losses5

Risk Exposure

Risk exposure value is calculated by the given formula:

Risk Exposure Value = Risk Probability * Risk Impact

The following table provides the possible exposure values:


Probability

Risk exposureColorRisk priority

0.050.250.50.750.950 - 0.75GreenLow risk

I

M

P

A

C

T

10.050.250.50.750.950.95 – 2.25AmberModerate risk
20.10.0.511.51.92.5 – 4.75RedCritical risk
30.150.751.52.252.85

Prioritization of risks must be done based on Risk Exposure value as follows:

  • If Risk Exposure value is Green (i.e. for Low Risks) Mitigation Plan or Contingency Plan are not obligatory.
  • If Risk Exposure value is Amber (i.e. for Moderate Risks) Mitigation Plan is required, Contingency Plan could be developed but is not obligatory.
  • If Risk Exposure Value is Red (i.e. for Critical Risks) Both Mitigation and Contingency Plans are required.
40.21233.8
50.251.252.53.754.75

Risk category

Risk sourceRisk Description/SummaryRisk ProbabilityRisk ImpactRisk ExposureRisk ExposureRisk statusRisk Treatment StrategyLast Update dateMitigation Plan
(Treatment strategy description)
AssigneeDate of Risk OccurrenceIssue Status Contingency PlanContingency Plan Assignee