New modules that need creation of new pipelines for bugfest as per Team vs module responsibility matrix.

Each module needs to comply with all points in Information needed for module deployment.

Deadline to complete all pipelines' development is Sprint 134 () Release integration week.


TeamModuleJIRA projectJIRA tickets to Teams to check against the  Information needed for module deployment.Team member working on it

Sprint 130

(20 Dec 2021)

Sprint 131

(10 Jan 2022)

Sprint 132

(24 Jan 2022)

Sprint 133

(7 Feb 2022)

Progress (%)Status
Thunderjetui-plugin-find-fund

UIPFF


Aleh Litasau+


100%Done
Firebirdmod-bulk-editMODBULKED

+


100%Done
ui-bulk-editUIBULKED


+

25%In progress
Bienenvolkmod-oaMODOA


+

90%In review
ui-oaUIOA



+


Thormod-inventory-updateMODINVUP



+


Knowledgewaremod-translations 





+

ui-translations







+