To have an known issue added to the Bugfest and Release Notes table, please add the labelknown-issue-morningglory. An issue will be removed from the list once the issue is Closed
NOTE: Only one sprint left for new development. Please update status, release, and/or split feature. If a feature is a MUST for Nolana and it is at-risk, please add the label nolana-at-risk to the feature.
Nolana - no change in release date (December 12)
Sprint 149: September 30 - Deadline for TC to accept new modules.
Sprint 150
New Development Freeze - Core (October 7)
New Development Freeze - Complete (October 14)
Sprint 150-
2
152
Nolana release hardening (initial)
Sprint 152 - Bugfest
Ways to help manage wrapping up new development for release
Dennis
Visuals
Wiki pages with test cases
More collaborative discussions with team to identify edge cases
Every release does not need to include new and major functionality. Sometimes you need to let the app/module breathe and focus on correcting bugs/defects, add more tests, and improve performance (if applicable).
Orchid Features Refinement
Sprint 150: Orchid scope finalized (proposed date October 10)
Features defined and reviewed with team
Development estimates
complete
complete
Sprint 152: Orchid new development officially begins [
TBD]
October 31 (based on module release deadline)]... but can start before...
Next steps:
1. Next week: POs will start to review features with development team.
2. KG will ask Oleksii to change scope finalization date to October 17.
Action item: Ask PC - about community prioritization