ACTION ITEMS:
Action items were aggregated from the retrospective board:
- Consider to use TestRail for subsequent Bug Fest runs
- Not all the areas of FOLIO were covered. Do next BF soon to cover them.
- Better scope definition is needed to avoid testing incomplete features.
- Always use real customer data.
- Original reference data must be migrated to the BF environment.
- Must have a planning meeting for every BF run: Define scope; Assign tasks to make sure that participants have time to complete them.
- Test cases for each module need to be reviewed with respective POPOs
- Discussion is needed about how long BF environment is staying up after test run is over.
- Discuss what should be bug handling workflow for the future BF runs.
Q&A:
Q: What happens next with the bugs?
...