Required Information in a New Environment Request

Basic Info (one-liners)

  1. Dev Team.  Who will be using the environment?
  2. Purpose.  Specific feature(s) being tested?

...

  1. Modules.  Primary module(s) related to the purpose of the environment.
  2. Expected Start Date
  3. Expected End Date

...

  • Or perhaps, during what flower releases’ development will it be needed?
  1. Data Set / Size. 

...

Justification

...

Justification

  1. Expand on the purpose as necessary.  Why is this new environment needed?
  2. Are there any existing environments serving the same team and/or modules?  If so, explain why they are not sufficient for this need.
  3. Cost estimates: a) monthly and b) total for the life of the environment.  
    1. Are there any past (or still existing) environments that were used in a similar manner, such that this environment would likely have similar monthly costs?
  4. Impact / risks if the request is declined.

Cost Management Plan

  1. Will the dev team be following the “pausing/stopping” guidelines?  Explain any planned divergence from those guidelines.
    • Refers to  “D4: Define guidelines/best practices around pausing/stopping environments when they're not in use - e.g. off-hours/weekends/etc.”
    • Specifically what will be the expected operating hours?  Or will it need to run 24/7?
  2. What budgets, budget alerts, cost anomaly detection will be used?

Approval Process

  • AWS Cost Review Group notified when Jira items moved to Submitted (how?)
  • Within two weeks: either approve, deny, or ask questions on the Jira.
    • PO and Dev Lead expected to respond to any questions, meet to discuss synchronously if requested.
  • Approval Checklist
    • Reasonable answers?
    • Reasonable answers?
    • All required fields submitted?
    • All Justification questions addressed?
    • Reasonable answers
    • ?
    • All Cost Management Plan questions addressed?
    • Reasonable answers
    • ?
  • Once approved, notify Treasurer (how?) to be aware of potential impact.

...