Attendees:  Khalilah Gambrell 

 TopicsTimePresenterAgenda/Notes
Announcements 10 minutes 

All 


Orchid release (NFR work) 15 minutes
Nolana Release - Key dates10 minutes Khalilah 

Key Stats to review:

NOTE: Only one sprint left for new development. Please update status, release, and/or split feature. If a feature is a MUST for Nolana and it is at-risk, please add the label nolana-at-risk to the feature. 

Nolana - no change in release date (December 12)

    1. Sprint 149: September 30 - Deadline for TC to accept new modules. 
    2. Sprint 150 (In Progress)
      1. New Development Freeze  - Core (October 7) 
      2. New Development Freeze  - Complete (October 14)  
      3. Sprint 150-152 
        1. Nolana release hardening (initial) 
    3. Sprint 152 - Bugfest
Product Owner recruitment15 minutesjulie.bickle