 TopicsTimePresenterAgenda/Notes
Announcements 10 minutes 

All 


Orchid release (NFR work) 15 minutes
Nolana Release - Key dates10 minutes Khalilah 

Key Stats to review:

NOTE: Only one sprint left for new development. Please update status, release, and/or split feature. If a feature is a MUST for Nolana and it is at-risk, please add the label nolana-at-risk to the feature. 

Nolana - no change in release date (December 12)

    1. Sprint 149: September 30 - Deadline for TC to accept new modules. 
    2. Sprint 150 (In Progress)
      1. New Development Freeze  - Core (October 7) 
      2. New Development Freeze  - Complete (October 14)  
      3. Sprint 150-152 
        1. Nolana release hardening (initial) 
    3. Sprint 152 - Bugfest

Ways to help manage wrapping up new development for release

  • Dennis
    • Visuals 
    • Wiki pages with test cases 
    • More collaborative discussions with team to identify edge cases 

Every release does not need to include new and major functionality. Sometimes you need to let the app/module breathe and focus on correcting bugs/defects, add more tests, and improve performance (if applicable). 

Orchid Features Refinement 
  1. Sprint 150: Orchid scope finalized (proposed date October 10)
    1. Features defined and reviewed with team 
    2. Development estimates complete
  2. Sprint 152: Orchid new development officially begins [October 31 (based on module release deadline)]... but can start before...

Next steps:

1. Next week: POs will start to review features with development team.

2. KG will ask Oleksii to change scope finalization date to October 17. 