Notes

Notes by David Bottorff

No Meeting Monday, We should have a quorum on Thursday

Holly

  • overview of capacity planning assignment

  • At current capacity, not all go features will be delivered by institutions' go live dates

    • adding developer capacity seems a bit late

    • will institutions need to alter their go live date or revise what they need at go live?

  • PO will review features needed for go-live, ask for SIG feedback, changes will be captured in Jira

  • Not only priority but also order in which features are being approached

  • deep dive for go live or first quarter after go live

  • may need to split features so that some elements are higher priority than others

  • cost of feature

  • show local team your recommendations to update local ranking

  • Assignment is due July 31, but stakeholders meet July 23, should higher priority epics be tackled first?

  • This will happen during SIG meetings after Washington DC meeting


Emma

  • ordering of checkout messages (non-circ policy, checkout notes, then multipiece) could have performance issues, would effect all items at checkout consensus is that short term reorderign is acceptable for the sake of performance to non-circ policy being last

  • anonymization - manual anonymization at patron request should all closed loans with fines/fees be excluded from manual anonymization okay? yes this seems ok