- Sprint retrospective agenda should be extended to cover sprint review topics:
- extra items added to sprint during the sprint
- wrong estimations that did not include some aspect
- raise discussion about carry over items 2+ times
along with regular retro discussion. Assignee: Oleksiy_Lemeshko
- Below tasks assignment approach should be followed by Core: Functional team members:
- look to the To Do column of Core: Functional Scrum Board in the current sprint for work to do before considering other stories. Please consider priority/order
- raise with Lead PO and/or SM if you're about to work on an item that is not in the sprint. Stand-up is workable channel
- if there is nothing for you in To Do list feel free to check highest backlog item that was previously refined (has estimation). Mention your intention during the stand-up
- Core: Functional team members to notify Tech Lead/SM about OOO plans
Above improvements will be added to Ongoing improvements section during next retrospective