Trillium (R2 2025)
Duration: 14 Sprints (mid Sprint 212 - mid Sprint 226) = 13.5 development sprint + 0.5 for modules releases
Roadmap
EPICS
Release preparation
Modules and Applications release
Trillium Bugfest Dashboard
Timeline
Sprint | Dates | Dates | Name | Description |
---|---|---|---|---|
Sprint 221 | Jul 25, 2025 | Notify community regarding sharing information of new modules | Include module to FOLIO Module/JIRA project-Team-PO-Dev Lead responsibility matrix | |
Sprint 222 | Aug 8, 2025 | Deadline for requests to add new modules to the reference environments | Create Jira ticket at FOLIO Jira project ex. FOLIO-3255: Add mod-inn-reach to testing/snapshot hosted environmentsClosed | |
Sprint 223 | Aug 22, 2025 | Umbrellaleaf R1 2026 release scope composition deadline | Lead PO prepared list of features for Sunflower R1 2025 release and input from SIGs | |
Sprint 224 | Sep 1, 2025 | API freeze for platform (Eureka/Stripes/RMB/Spring) readiness review | RC review released platform components and facilitate meeting with unreleased components owners to discuss available impediments/issues/problems to understand when component could be released | |
Sep 5, 2025 | API freeze for platform (Eureka/Stripes/RMB/Spring) | Okapi/Stripes/RMB/SpringWay freeze and deadline for initial releases of platform components. No breaking changes to the platform after this date. Feature development freeze for R2 2025 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R2 2025 period. Separate release branch has to be created after feature freeze date. All R2 2025 bug fixed have to be applied to both release and Master branches. Next R1 2026 release period feature development is expected on Master branch. | ||
Features test cases preparation deadline | To start test case automation for Trillium features test cases need to be prepared. | |||
Deadline for acceptance of new modules by Technical Council at Trillium (R2 2025) | New Module Technical Evaluations - Technical Council - FOLIO Wiki | |||
Sprint 225 | Sep 8, 2025 - Sep 19, 2025 | Teams upgrade to the platform components | Teams upgrade to the platform components versions that were released. | |
Sep 8, 2025 | Bugfest environment preparation kick-off | Conduct meeting for review Bugfest preparation plan Create appropriate jira tickets in Kitfox backlog Review list of new modules Review data cleanup Review new data | ||
Sep 11, 2025 -Sep 12, 2025 | Umbrellaleaf release scope decomposition and estimation |
| ||
Sep 15, 2025 | Umbrellaleaf R1 2026 release scope refinement deadline | POs prepare list of UXPROD features aligned with Umbrellaleaf R1 2026 team capacity. PO present prepared scope at next PO Weekly meeting at <TBD> | ||
Sep 19, 2025 | Major interface version provided to be updated |
| ||
Review upgrade to platform components status. | RC review upgraded components and facilitate meeting with non-upgraded components owners to discuss available impediments/issues/problems to understand when component could be upgraded | |||
Modules feature development freeze R2 2025 | Feature development freeze for R2 2025 release period. No new feature can not be added after this date. DoD for features has been met. Only defects are expected tie to R2 2025 period. Separate release branch has to be created after feature freeze date. All R2 2025 bug fixed have to be applied to both release and Master branches. Next R1 2026 release period feature development is expected on Master branch. | |||
Trillium R2 2025 features acceptance deadline |
| |||
Sprint 226 | Sep 22, 2025 - Sep 24, 2025 | Schema upgrade testing | Major modules versions should be released. Schema upgrade have to be released and tested locally by each team. | |
Sep 22, 2025 - Sep 26, 2025 | Teams modules releases |
| ||
Sep 25, 2025 (Thursday) | Modules release readiness review | RC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released). Major interface version provided to be updated | ||
Sep 22, 2025 | New blank Trillium bugfest environment is prepared |
| ||
Sep 24, 2025 | Scripts are ready for new modules deployment |
| ||
Sep 25, 2025 | Schema upgrade testing review | RC review upgraded modules and facilitate meeting with non-upgraded modules owners to discuss available impediments/issues/problems to understand when schema could be upgraded. | ||
Sep 26, 2025 | Final Review modules release readiness | RC review released modules and facilitate meeting with unreleased modules owners to discuss available impediments/issues/problems to understand when module could be released | ||
Module release deadline | All modules must have R2 2025 compatible releases by this date | |||
Finalize release notes for Trillium features/applications/modules | Release notes have to be updated | |||
Sep 26, 2025 | Contact with EBSCO FSE devops | Review release information. Up to date versions should be set | ||
Sep 27, 2025 - Oct 3, 2025 | Release integration week | Bugfest environment preparation, testing of schema and data migration by EBSCO FSE team | ||
Oct 1, 2025 | Deployment to Trillium bugfest env is completed. Data set is ready |
| ||
Oct 2, 2025 - Oct 3, 2025 | Sanity testing at Trillium bugfest env |
| ||
Sprint 227-228 | Oct 6, 2025 | Umbrellaleaf R1 2026 RFC Consideration | tech-council/NEW_MODULE_TECH_EVAL.MD at master · folio-org/tech-council · GitHub | |
Oct 6, 2025 - Oct 31, 2025 | R2 2025 Release testing and hardening period |
| ||
| Oct 6, 2025 - Oct 24, 2025 | Functional testing (Bug Fest) | Execute all TestRail test cases | |
| Sep 22, 2025 - Oct 24, 2025 | Performance testing |
| |
| Oct 27, 2025 - Oct 31, 2025 | Ongoing triage and bug fixing of bugs begins immediately |
| |
Oct 30, 2025
| Bugfix releases readiness | RC review bugfix dashboard and facilitate meeting with unresolved modules owners to discuss available impediments/issues/problems to understand when module could be released | ||
Create R2-2025 platform complete release branch | TBD | |||
Oct 31, 2025 | Bugfix releases deadline |
| ||
Sprint 229 | Nov 4, 2025 - Nov 6, 2025 | Final Smoke testing |
| |
Nov 10, 2025 | Release is public |
|