2025-04-21 Release Management Stakeholder group

2025-04-21 Release Management Stakeholder group

Release Management Stakeholder group

Attendees Mark Veksler Yogesh Kumar Khalilah Gambrell Oleksii Petrenko Stephen Pumpell


https://openlibraryfoundation.zoom.us/j/88356244681?pwd=aFo1cEhVam1ENTN1ZHFOZWg0V1Jxdz09


Meeting Time: 9:00 AM Eastern Time

Discussion items

Time reservedDescriptionPresenterDetails/Comments
15 min

Sunflower Release Timeline

Oleksii/Yogesh

ECS testing has progressed successfully, with approximately 5,500 manual test cases executed and a 95% pass rate, accounting for deferred defects.

However, due to delays in the community’s testing of non-ECS functionality, we are not yet in a position to announce a GA date for the Sunflower release. We estimate that non-ECS testing will be completed within the next 2–3 weeks.

We will reassess the situation at the next Release Management Group meeting, and based on the number and severity of outstanding defects from non-ECS testing, we will determine an appropriate General Availability (GA) date for the release.

The Sunflower non-ECS testing is still in progress. We need to revisit the date for the Sunflower after the tests are complete.

Number of unresolved P1&P2 defects is around 25 