Time reserved | Description | Presenter | Details/Comments |
5 min | Review Poppy CSP#2 status | Oleksii | |
10 min | Review and make decision for Ramsons release plan | Oleksii | Duration sprints: 15 (mid Sprint 187 - mid Sprint 201)
UAT Sprint - Sprint 199-200 =============================== Start: mid Sprint 187 Features Development Freeze: Sprint 200 September 27 Modules release week: First part Sprint 201 September 30 - October 4 Bugfest: Sprint 202-203 October 14 - November 1 GA: November 18, Sprint 204 Approved |
5 min | OKAPI braking changes for Q release | Jakub Skoczen | Decision:
|
5 min | Extend TCR review for Q release | Charlotte Whitt Owen Stephens | Initial deadline for TCR review March 1. Request to expend TCR review deadline to March 15. No objection from RMS panel Serial Manager related functionality: Can TC review it up to March 15? → Jakub Skoczen to discuss with TC |